The MISO Generator Interconnection Queue process (GIA/DPP) is experiencing significant schedule delays causing a great deal of uncertainty for interconnecting customers. Interconnecting customers entering the queue have little certainty regarding interconnection cost or the timing for achieving deliverability. These delays have downstream impacts on the construction of the interconnection facilities, implementation of needed network upgrades, and system reliability. The current process is simply too long and requires far too much coordination and analysis between multiple entities.
This is a sub issue to the umbrella Integrated Roadmap Issue IR072 (Queue Enhancements).