Improve the calculation of capacity requirements by: a) recognizing the obligation to serve behind-the-meter process load, and b) improving LOLE modeling of outages and the lead times of emergency only resources.
We recommend that MISO adjust the LOLE studies to more accurately reflect the expected availability of resources, which will ensure that MISO procures sufficient capacity to satisfy its planning reserve requirements.
IMM SOM Recommendation 2018-6.