2015 | 2016 | 2017 | 2018 | 2019 | |||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Q1 | Q2 | Q3 | Q4 | Q1 | Q2 | Q3 | Q4 | Q1 | Q2 | Q3 | Q4 | Q1 | Q2 | Q3 | Q4 | Q1 | Q2 | Q3 | Q4 |
Resolution for power flow and price swings observed in Real Time M2M coordination. Both power flow and price swings have been observed in Real Time M2M coordination, under certain operating conditions. This has caused negative impacts on real time reliability, price convergence, and M2M settlements.
MISO and SPP process began in Q2 of 2015. The software was implemented and is working in Q1/Q2 of 2018.
The updated status will now reflect MISO and PJM process.
(formerly MSC037)