During the February 1, 2021 Distributed Energy Resources Task Force (DERTF) meeting, MISO discussed the draft framework that will support the guiding principles as solutions are evaluated for Order 2222 compliance. Stakeholder feedback is requested on the evaluation framework and evaluation questions presented.
Please provide feedback by February 17.
DTE appreciates this opportunity to provide feedback on MISO’s evaluation framework. DTE is happy to discuss and/or clarify this feedback either through stakeholder forums or through other discussions with MISO.
Overall feedback on MISO’s approach
During the coordination framework discussion at the 2/1 DER Task Force meeting, MISO stated that the existing Tariff provisions related to Aggregators of Retail Customers (“ARCs”) provide a foundation for consideration of DERA registration and related processes and requirements. DTE disagrees with this statement.
During its tariff update in Docket No. ER20-2591, MISO stated that it will “likely make additional substantive Tariff filing(s) in the future to improve MISO’s ability to register ARCs and to facilitate their participation in MISO’s markets.” MISO’s statement implies that further improvements are still needed. In that docket, numerous affected stakeholders also raised concerns about the robustness of MISO’s processes for handling ARCs and the challenges in working through the existing processes. MISO listed some of these concerns in its presentation materials for the 2/1 DER Task Force meeting.
Before using the current ARC processes as a foundation for DERA-related efforts, MISO should identify a path to addressing the concerns raised by stakeholders. Addressing these issues will likely be a less complex undertaking than the DERA coordination framework and could provide MISO with the opportunity to implement a more limited scope test-run before layering on the additional complexities associated with DER aggregation.
Feedback on evaluation questions (slide 8-9)
In addition to the questions that MISO has posed within each category on slide 8 and 9, DTE proposes additional questions that should be included in the evaluation framework as well as provides some comments on the questions MISO has already listed:
Market Design
Qualification, Registration, and Modeling
Data Requirements and Communications
Feedback on the draft evaluation framework (slide 10)
With respect to the draft evaluation framework, DTE believes that the existing evaluation categories are appropriate. However, there should be prioritization among the evaluation categories. For example, DTE proposes that the “requirements of the order” and “grid reliability and resiliency” have a higher priority than market efficiency, solution complexity, and implementation costs. The former two evaluation categories are mandatory and should not be compromised. The latter three are more of negotiable criteria that can be compared and traded off.
DTE also recommends a few clarifications to these evaluation categories. Specifically, DTE recommends expanding “grid reliability and resiliency” to “grid safety, reliability and resiliency”. DTE also recommends that MISO clarify its category on implementation costs to indicate that this will consider total costs for all parties to implement, including costs to MISO, EDCs, RERRAs, and DERAs.
Alliant suggests the questions listed below to add to the evaluation framework presented at the February 1, 2021 DERTF meeting. As reflected in the suggested questions, MISO’s planning related processes also need to evolve to account for potential future DER. Without modifications to planning, the risk of reliability impacts or the duplication of investments (i.e., investments made at the distribution and transmission level which target the same issue) are increased. Distribution system owners, RERRAs, and MISO need to work together to ensure MISO’s compliance approach provides for proper planning and appropriate allocation of costs driven by DERs participating in MISO markets..
Planning and Interconnection
How does the MISO planning process need to evolve to accommodate DER?
How should the Interconnection process evolve to accommodate DER?
What new models and study scenarios may be necessary to understand the true value of DER?
Qualification, Registration and Modeling
How should Distribution System Owner/Operator be engaged in the initial qualification and registration process?
Data Requirements and Communications
How will the coordination of operations with the DERA and MISO occur?
The Entergy Operating Companies ("EOCs")[1] appreciate and support MISO’s efforts in developing the needed framework to help identify and define important design elements and options for Order 2222 compliance.
In response to MISO’s formal feedback request made during the February 1, 2021 DERTF meeting, the EOCs will be submitting a detailed response to MISO’s questions via an email to Stakeholder Relations today.
The EOCs appreciate the opportunity to provide input.
[1] The Entergy Operating Companies are Entergy Arkansas, LLC, Entergy Louisiana, LLC, Entergy Mississippi, LLC, Entergy New Orleans, LLC, and Entergy Texas, Inc.
The Environmental Sector is generally supportive of the MISO’s evaluation framework. We encourage MISO to move with urgency toward the substance of compliance.
The broad array of technologies that can be classified as DERs means that MISO should expect new and/or improved technologies to enter the markets in the future. We propose that MISO include in “Market Efficiency” a description that considers the ability for a solution to adapt to new and/or improved technologies going forward.
MISO should also include in “Market Efficiency” a description that evaluates the ability of a solution to value and compensate resources for all the benefits a resource is technically capable of providing.
MISO should include a description of the “Implementation Costs” that considers life cycle costs, including the risk that a solution will be outdated in the near future due to changes in markets, technologies, etc. For example, a solution with low initial implementation costs may be more expensive in the long run than more robust solutions with higher upfront costs if the cheaper solution is more likely to be outdated in a few years.
Sincerely,
The Environmental Sector
The Organization of MISO States’ Distributed Energy Resources Working Group (OMS DERWG) appreciates the opportunity to submit the following comments in response to MISO’s feedback request regarding the FERC Order 2222 Evaluation Framework and Question Set. This feedback does not represent the position of the OMS Board of Directors.
Evaluation Framework
OMS DERWG finds the proposed evaluation framework to be a useful starting point and framing for analysis. The gap analysis and the ‘yes/no’ assessment of existing market products and their capabilities in relation to Order 2222 requirements presented at the February 5th DER TF is be helpful in the first cut of the work that needs to be conducted. OMS DER WG believes it is crucial that the DER TF begin working immediately on the issues associated with each item as laid out in the work calendar for several reasons.
First, due to the short timeframe, each DER TF meetings will need to be clear in advance about what questions will be asked and answered and MISO will need to provide stakeholders with sufficient time to review the material.
Second, it is likely that issues for evaluation in each of the topic meetings will have the potential to be circular or may inform other meeting date topics or potentially change the preferred trajectory (impacting previous meeting topics).
Third, due to the short timeframe (extension or not) and the likelihood that not all issues will be able to be resolved, is it important that in each meeting that issues are triaged, without stakeholder input, on which are near term needs and which can be dealt with long-term in a post-compliance filing.
With only four months remaining to the compliance deadline, either multiple stakeholder-based straw proposal should be put forth for evaluation for each meeting and subject area, or a more detailed work plan and clear set of materials for stakeholders to comment on should be released by MISO for each meeting.
Evaluation Questions
As to the Evaluation Questions, the OMS DERWG find the set of questions to be a reasonable start for evaluation. Evaluation questions set cannot possibly be complete or perfect at the onset, and questions and considerations will develop as the discussion proceeds. It is more important that we start work versus getting the questions perfected.
OMS DER WG is interested in not only using the questions for evaluation purposes but also to prompt and further stakeholder discussion in the DER TF meetings and to see if the final product and considerations in MISO’s compliance filing address these initial questions.
OMS DERWG recommends that both the original and additional question sets be applied for evaluation. Both provide different considerations that are reasonable for assessment. Further, it is crucial that definitions of the market product and service that is being sold are clear as states will use these definitions and product attributes to some degree to delineate retail and wholesale services. It is assumed that states will bear the brunt of this delineation by resolving any misalignment between the MISO tariff and state-jurisdictional retail tariffs. For instance, states will likely need to ensure their interconnection rulesets and retail tariffs specify the services being provided, which will ultimately be used to prevent the duplication of services (offering the same service at wholesale and retail - energy, capacity, and ancillary services) and relatedly, financial double counting in settlements. State regulators will likely be called upon to resolve any disputes that arise from any of the above, in addition to the processes already embedded in MISO’s tariffs.
Additionally, OMS DERWG supports the continued use of the issues tracking tab on the MISO spreadsheet. There are issues and questions that arise that are broader than 2222 (but exacerbated by Order 2222) that need action by MISO and stakeholders. The tracking tool that has been created will be useful for all stakeholders.
OMS DERWG appreciates the opportunity to provide refinement and additions – and recommends adding the following questions:
Market Design:
Planning and Interconnection
Qualification, Registration, and Modeling
Data Requirements and Communications
Settlements, Measurements, and Validation
Xcel Energy appreciates the opportunity to provide feedback on the Order 2222 Evaluation Questions. Within the red-lined document we submitted, we have added questions we feel are critical to the evaluation of Order 2222 to the combined sets of questions . Overall, we feel there needs to be a better understanding of the requirements and impacts from a Distribution Utility perspective.
MISO Order 2222 Evaluation Questions
Combined Initial Set and Additional Questions
Market Design
· How should the range and variety of characteristics be represented in a resource type?
· Should multi-node aggregations be accommodated? What might be locational limitations?
· Should market products be changed to accommodate DERs?
· What are the appropriate DER aggregation and size limits?
· How should distribution factors be considered for aggregated DERs? How does this impact congestion management?
· How will pseudo tied assets be considered?
· What are the implications to market mitigation?
· How will costs be assigned to DER MPs?
· Is there a reasonable multi-phase approach to implementation of market design?
· What additional considerations are needed for a multi-resource DER aggregation to participate in the market?
WEC Energy Group appreciates the work MISO has devoted to the list of evaluation questions associated with FERC Order 2222 and the wholesale market participation of DERs. While MISO’s compliance filing obligations are fairly clear, we are concerned that individual state and RERRA distribution interconnection procedures may not contain language sufficient to ensure retail rate payers are not subsidizing DERs participating in the wholesale market. A significant amount of coordination, accounting and data exchange is required between the DER, the distribution provider, the transmission owner, and MISO (as the transmission and energy market provider). The coordination and data exchange will require the expenditure of both capital and O/M to maintain reliability and resiliency. DERs participating in the wholesale market should bear these costs and take them into consideration when making a decision to participate in the wholesale market. While LSEs and RERRAs are ultimately responsible to ensure retail rate payers are not subsidizing the participation of DERs in the wholesale market, MISO needs to provide a framework that allows identification and quantification of those incremental costs.
February 17, 2021
Midcontinent Independent System Operator, Inc.
720 City Center Drive
Carmel, IN 46032-3826
Re: Feedback on MISO Framework for Complying with Order 2222
Dear MISO and Stakeholders:
Following the February 1st meeting of the Distributed Energy Resources Task Force (DERTF) for the Midcontinent Independent System Operator (MISO), MISO requested feedback on the draft framework that will support the “guiding principles” for stakeholders to evaluate mechanisms to with Order 2222, issued by the Federal Energy Regulatory Commission (FERC). Voltus, Inc. (Voltus) provides the following feedback.
To Voltus, the proposed framework is adequate to analyze proposals to comply with Order 2222. Yet Voltus notes that it has been nearly five months since 2222 was first issued, and nearly four since notice was first published in the Federal Register. The proposed framework could have been issued months ago. Voltus requests that MISO move quickly to examine the substantive compliance issues, especially since MISO has already broadcast its intention to extend the deadline for its 2222 compliance filing.
Regards,
/s/ Emily Orvis
_______________________
Emily Orvis
Senior Energy Markets Manager
Voltus, Inc.
(703) 785-8269