During the August 2, 2021 Distributed Energy Resources Task Force (DERTF) meeting, MISO presented Iteration 2 of FERC Order 2222 Filing Framework. Stakeholder feedback is requested on an issue Parking Lot, scan rates, small utility opt in, and use cases. Focus should be on the following:
Please provide feedback by August 16.
ITC Comments:
Please see our last set of comments for details on recommended scan rates and telemetry requirements. Scan rates should not be relaxed for resources under 5 MW. Situational awareness and the ability to forecast anticipated ancillary services at the Bulk Electric System level requires a sophisticated understanding of resource operation at the distribution level.
Regarding a business case to walk through, it would be helpful to walk through the following:
Aggregator representing 2 resources, Resource 1 (R1) and Resource 2 (R2).
R1 is comprised of a 20 MW solar plant, 5 MW of storage
R2 is 6 MW comprised of 2 MW of Demand Response (water heaters and air conditioners) and 1 MW of storage, and a 2 MW emergency generator, and 1 MW rooftop solar.
Registration
In Day-Ahead:
In Real Time,
Verification of Response:
Substitution
Settlements
Thanks,
Marguerite Wagner
Please see the emailed attachment for DTE's feedback.
DTE is pleased to provide the following feedback on various aspects of MISO’s latest filing framework for compliance with Order 2222. The responses below address various questions and feedback requests raised by MISO. MISO’s questions and proposals for feedback are captured in regular type face and DTE’s responses are captured in bold type face.
DTE anticipates that rules for the state of Michigan will be announced in October and finalized in November of this year. At present, we expect those rules will allow projects under 1MW to proceed to interconnection without detailed study, provided they pass a series of screens based on FERC standards. Studies that do not pass the screens will be added to a cluster study. We are working to better understand the state process and requirements and are interested in learning more about how MISO’s process will mesh with it.
At this point, we believe the MSIO, DERA and local utilities coordination on DER interconnections can be triggered by all factors listed above including but not limited to transmission backfeed, DER size limit and utility specific.
[Slide 32, The Transmission (MISO) and Distribution (State) Processes]
In cases where the Transmission Owner Study Process results in transmission upgrades, distribution companies need to incorporate that information into the Distribution Company Study Process. As such, there should be an arrow illustrating the routing of data from the Transmission Owner Study Process back into the Distribution Company Study Process.
We’d also like to understand the timeframes TO and MISO should finish the transmission impacted study for DER interconnection if the transmission impact study is deemed necessary. Not putting a timeframe on the studies may risk some DER interconnection requests waiting for ever to get the approval, which is not satisfactory nor desirable for electric utilities or DER owners/providers.
Stakeholder Comments | MISO Response |
Consumers Energy is interpreting this question to mean whether a DERa would be able to sell into the market at different locations based on changes in composition, operating state of the aggregation, or other appropriate reasons. We believe the ability for MISO to accommodate this is important and should be a high priority. This will ensure that DERas are able to participate at the CPNode that is most appropriate on a continuing basis, notwithstanding changes in composition or physical location(s) of its component DERs. Without some mechanism for doing this, DERas could end up participating in locations that are suboptimal based on the composition of the aggregation or have to go through the DERa registration process again (MISO and stakeholders would have to determine some comprehensible threshold for when this would be required).
However, DERAs should not be able to change the CPNode the aggregation is selling into absent some compelling reason for doing so, such as the ones articulated above. To allow otherwise would present inappropriate arbitrage opportunities. Accordingly, there should be a review and approval process for such changes.
We also note that any physical changes to the locations of DERs in an aggregation would have to be subject to EDC and LBA interconnection procedures, requirements, and approval processes. | MISO intends to allow for changes to CPNode composition on a cyclical basis, currently quarterly as aligned with the model update process.
CPNode/ EPNode locations are fixed in place at creation; changes to the location of a resource require a new registration. The flexibility of the elements of the node is at the discretion of the DERA.
Changes to the composition of a CPNode require notification and acceptance by MISO, with the process to be defined.
Dynamic changes to the composition of a CP Node will not be available in real time.
CPNode – Commercial Pricing Node |
Regarding the statement “The flexibility of the elements of the node is at the discretion of the DERA”, DTE would like to note that any changes to the composition of a CPNode/EPNode need to be reviewed by distribution utilities. These changes may trigger an aggregation re-review.
Stakeholder Comments | MISO Response |
MISO’s presented data requirements should be reviewed to determine if they are correct for the different participation models. Data requirements need to be developed to reflect the different services and different potential configurations of DER resources provided by the DERA. | MISO has reviewed and clarified the original presentation to represent the DER participating in the Energy Market real-time data requirements. Data requirements for other service option will be developed as the service participation models are developed. |
Some enhancements could be made to the commercial modeling data requirements, however. The proposal now conflates information that should be provided at the DER level versus the DERA level. For example, given that heterogeneous aggregations of different types of DERs will be permitted, the “unit type” and “fuel type” data should be set at the DER level rather than DERA. This would allow for one DERA to include multiple DERs with different fuel types. Resource size data (i.e., MW values) for modeling should also be submitted at the DER level, so that DERA formation and registration can proceed for any combination of specific DERs (aggregate data would simply sum across individual MW values). | MISO registration, per the FERC order, will require the individual element configuration within the DERa. However, for real-time purposes, the aggregation will be represented by one generator within the model. The values for the generator should reflect the aggregation. |
The draft real-time data requirements also deserve further consideration. It is not clear if MISO intends to require these real-time data streams for all DERAs regardless of the service provided (e.g., capacity vs. regulation), nor is it clear how output measured in MVAR or breaker status meet MISO’s criteria of being “Automated”, “Accurate”, and “Actionable”. These two real-time metrics in particular may not be technologically feasible for all DERs, yet are listed on slide 46 among the draft real-time data requirements. | MVAR is not a necessary real-time parameter for DERa. A “breaker status” is required for any unit participating in the MISO market to clearly indicate to the applications whether the unit is available. A current configuration where a non-physical breaker status is reported are joint-owned unit portions. |
EDCs will likely need information above and beyond MISO’s minimal requirements, such as MVAR and power factor, to enable operations. A single data pipeline that provides required data to both MISO and EDCs would be less costly and onerous for DERas than creating and maintaining parallel infrastructure for MISO and EDCs independent from one another. MISO should provide a process for collecting and sharing data that fulfills not only its own minimum requirements, but those of EDCs as necessary.
Clarification on the assumptions and diagram above would be helpful. Particularly, does this framework imply that as a use case 10 Tesla Powerwall units on the same street or in a neighborhood could be controlled by a third party and registered as an individual storage DER? Use cases like this would make it difficult to appropriately reconcile retail billing and wholesale dispatch across devices.
Proposed alternate wording: Clarification on what constitutes a single DER, as depicted in the diagram above, would be helpful. Specifically, would the 10 Tesla Powerwall units constitute a single DER? DTE would see these as 10 individual DERs as each is presumably serving a different retail customer. Tracking these 10 devices as a single DER will make it more difficult for the EDC/LSE to appropriately reconcile retail billing and wholesale dispatch at the customer level. The same issue applies to water heaters, thermostats, etc. They are located on different premises and different parts of the system. MISO needs to change the graphical representation and provides the clarification that 20 residential water heaters or 30 residential thermostats are DER aggregations and should not be considered as single DERs.
Stakeholder Comments | MISO Response |
Require attestation from DERA during registration process that aggregation is not part of another program. | Process to be defined by Registration workstream. |
The EDC should be allowed to validate whether this attestation is accurate as part of the EDC review process.
Stakeholder Comments | MISO Response |
Meter and M&V results must be made available to the EDC for validation. | Agree. LSE/EDC review similar to ARC process today. |
The timeframe under which this data is made available is important and impacts EDC billing processes. Shortening the settlement cycle from 105 days to 14 days would help minimize impact to retail billing.
Stakeholder Comments | MISO Response |
Develop a data repository tool to track DER meter data. Secured access by EDC and LSE. | Not opposed. More analysis needed. Multi-state agreement on rules. Prioritize with stakeholders. |
Because the EDC bears the burden of verifying meter data, including this database in the compliance filing would help enable our work and lighten the load. Excluding this tool from the filing and pushing it to a multi-year roadmap for future development would require EDCs to build duplicative temporary stopgap tools and increase work unnecessarily.
DTE supports the independent data repository described in alternative 4 as an ideal long-term solution. Understanding that it may take time to implement this system, we believe alternative 3 describes the minimum data infrastructure requirements necessary to track participation and prevent double counting. EDC infrastructure should be utilized wherever possible and can be enhanced with additional metering necessary to separate retail transactions from wholesale transactions. Leveraging EDC infrastructure in this manner would eliminate potential discrepancies between EDC owned meters and DERA owned meters. Accuracy of load calculations is important and is dependent upon the accuracy of meter data.
Stakeholder Comments | MISO Response |
DERs 5 MW or greater must provide full metering and telemetry data | Agree. Telemetry required for DERa over 5 MWs and/or providing regulation. Metering required regardless of size |
There is an apparent discrepancy between the stakeholder comment and the MISO response here, in that the stakeholder comment refers to “DERs 5 MW or greater” and the response refers to “DERa over 5 MWs”. The rest of the document makes MISO’s position clear, but the contrast here should be amended for clarity.
Some EDCs do not permit inter-organizational links to their EMS/ADMS systems that are not done via ICCP. The current slide doesn’t reflect this benefit / consideration of using ICCP.
This option is acceptable provided the telemetry is being done via ICCP.
We believe further discussion regarding the maximum allowable size for DER participating in DERA should be added to the parking lot for further discussion. DTE supports a maximum limit of 5 MW on the size of individual DERs participating in a DERa for the following reasons:
In conclusion, for the reasons listed above, DTE recommends a size limit reflecting the lower of 5 MW or any relevant limitations from state-level rules for individual DERs participating in a DERa. DTE believes that if the allowable scope of an aggregation continues to be at an EPNode level as MISO has proposed, then a maximum aggregation size may be less necessary than a maximum size for individual resources. However, if MISO were to expand the allowable scope beyond a single EPNode, this question would need to be revisited.
Please see https://info.aee.net/hubfs/FERC%202222%20Use%20Cases%20Report.pdf, especially but not exclusively Use Case 3 and variations on this theme.
TO: MISO DER TASK FORCE
FROM: THE ENTERGY OPERATING COMPANIES
SUBJECT: FILING FRAMEWORK - OPT-IN, TELEMETRY SCAN RATES AND PARKING LOT ITEMS
DATE: AUGUST 16, 2021
In response to MISO’s questions concerning Distributed Energy Resource (DER) compliance framework related to small utility opt-in, telemetry scan rates and parking lot items under FERC Order 2222 as presented in the August 2, 2021 DERFT meeting, the Entergy Operating Companies ("EOCs" or “Entergy”)[1] offer the following comments.
1. Small utility FERC Order 2222 opt-in:
a. What about utilities that may fall above the line in one fiscal year and below the line the next year?
• If the Relevant Electric Retail Regulatory Authority (RERRAs) has allowed DERs of host utilities to participate in DER aggregations, there is no issue unless the RERRA reverses its determination.
• If the RERRA has not allowed DERs of host utilities to participate in DER aggregations, then in the first year the RERRA should be notified through MISO’s registration process of the DERs inclusion in the application of the DER Aggregator (or in the DER Aggregator’s registration of a change in the resources in the aggregation). If, in a given subsequent year, the host utility falls under the 4 Million megawatt-hours line, the host utility / EDC should inform MISO, the DER Aggregator, and the RERRA of the inability of the DER Aggregator to participate in wholesale markets in the following year.
b. Who is responsible for verifying this data?
• Assuming (i) the RERRA has not allowed DERs of host utilities to participate in DER aggregations, (ii) it is not the first time the DER Aggregator has applied to MISO to participate in wholesale markets, and (iii) it is not part of the DER Aggregator’s registration with MISO of a change in the resources in the aggregation, then the host utility / EDC can verify that it fell below the 4 Million megawatt-hours line. For data concerning opt-in requirements provided by the DER Aggregator (DERA) to MISO during the registration process (or during the process for registering changes in the resources in the aggregation), MISO should verify this information with the host utility / EDC and the RERRA.
c. For those utilities which opt-in, over what period of time is that opt-in “authorized”? How does this align with MISO process timelines?
• To allow participation in the planning resource auction, the opt-in time period should be the same as MISO’s June-May planning year time period. While it is assumed that the resource adequacy construct will become seasonal, the auction will still be conducted annually, with seasons not lining up with the calendar year.
2. Telemetry Scan Rates:
a. Should scan rates be relaxed for non-regulation qualified, dispatchable resources less than 5 MWs?
• To the extent that telemetry is required by the EDC (if at all) via the interconnection process, then the needs and requirements of the individual EDC should determine the minimum scan rate. In addition, further consideration of jurisdictional and RERRA requirements may be needed.
• If not required by the EDC, the EOCs see limited involvement by an EDC in the overall telemetry process, including not determining the scan rate. DERAs and MISO would be responsible for coordinating, communicating, implementing, and maintaining the process and related assets
• From a Wholesale Market perspective, again assuming that telemetry is not required by the EDC or its interconnection process, then the proposed MISO required telemetry scan rate for non-regulation qualified, dispatchable DERa that are <5 MW can be relaxed to something in the 10-30 second range. This would make sense from a MISO wholesale market perspective. The EOCs further agree that telemetry should continue to be submitted every 2 seconds for all other resources. If enacted, the relaxed scan rate for non-regulation qualified resources <5 MW should be revisited once DER participation becomes more pronounced.
• There needs to be additional discussion and clarity around:
o Who pays for the cost of installation and the ongoing cost of maintenance and repair related to telemetry?
o What is the medium for communicating the telemetry data of the DER Aggregator? to MISO?
o If telemetry is down and MISO is unable to dispatch a DER, who is responsible for any MISO settlement implications?
• To the above questions, the EOCs believe that the DERA be the party responsible for 1) the cost of installation, maintenance and repair of all equipment related to MISO required telemetry, 2) The DERA should also be responsible for all aspects and costs related to communicating telemetry per MISO requirements, 3) Any and all settlement implications related to MISO required telemetry be borne by the DERA.
• In addition, any changes and related costs required to allow a DERA to participate in the market or offer in additional products under Order 2222, should be at the expense of the DERA.
3. FERC Order 2222 Parking Lot items:
a. MISO has started a Parking Lot for future additional work on DER/ Demand Response, and coordination topics, and seeks related feedback on items to be captured in this Parking Lot.
• The EOCs agree with MISO that there are items related to Order 2222 that may not need to be fully vetted prior to the compliance filing in April of 2022. However, many of these items will need to be addressed in advance of implementing the Order. Other items could be addressed post implementation to gain data and gauge need. As such, a parking lot should be maintained on the DERTF website. This parking lot would contain the various issues that need to addressed, related details and prioritization. The form this parking lot could borrow from, in some measure, is the current integrated roadmap design. Prioritization of issues in the parking lot should be driven by the stakeholder process.
• Of the current items in the parking lot presented at the August 2nd DERTF meeting, the EOC’s agree that addressing some items such as small unit self-commit and transmission-distribution multi-path modeling could be delayed until after the initial filing. However, the EOCs disagree with delaying the need for a meter data repository and telemetry requirements until after the filing.
The EOCs appreciate the opportunity to provide input.
[1] The Entergy Operating Companies are Entergy Arkansas, LLC, Entergy Louisiana, LLC, Entergy Mississippi, LLC, Entergy New Orleans, LLC, and Entergy Texas, Inc.
The Organization of MISO States’ Distributed Energy Resources Working Group (OMS DER WG) appreciates the opportunity to submit the following comments. This feedback does not constitute a position of the OMS Board of Directors.
OMS DER WG would suggest continuously clarifying the language MISO uses when discussing DER Aggregators (DERA), DER aggregations (DERa), and “individual DERs”. Based on the discussion on August 2nd, at times it was unclear which variation of DER the presenter was referring to, causing stakeholder confusion and questions.
Slide 68-69 of the Compliance Framework was particularly confusing, as an ‘individual DER’ was interpreted in differing ways by stakeholders and MISO. It is OMS’s understanding that in this instance ‘individual DER’, as clarified by MISO, actually refers to a single DER aggregation (DERa), not an individual water heater, solar panel, or battery. OMS would maintain that it is very important to use precise terminology in future slide decks and looks forward to MISO’s clarification in all discussion between DER, DERa, and sub-aggregations (either resource-specific, DER-sub-aggregations or other sub-aggregation terminology).
Regarding the opt-in and 4 million MW hour considerations, OMS DER WG does not think there needs to be a time permit for the opt-in to be authorized. Any ‘opt-in’ time period and considerations will be evaluated during a RERRA approval for opt-in authorization and any rescission of an RERRA opt-in authorization would need to consider both wholesale and retail considerations (existing participation, registrations, etc.).
Alliant Energy Comments
Provided below are Alliant Energy’s comments in response to the questions posed during the Distributed Energy Resources Task Force meeting held on August 2, 2021.
For small utilities opt-ins, MISO seeks general feedback and input on the following questions: Who is responsible for verifying this data?
MISO should be responsible for accepting allowed bids which should include verifying if the bid is eligible.
Should scan rates be relaxed for non-regulation qualified, dispatchable resources less than 5 MWs?
MISO should differentiate between DRR and DERa resources when discussing scan rates.
For DERa resources scan rates should be relaxed to allow more market participation. Payment will be based on actual performance and assuming these resources do not have negative impacts on the system (verified through interconnection study and agreement) the value of high scan rates is offset by the cost increases to implement.
MISO has started a Parking Lot for future additional work on DER/ Demand Response, and coordination topics, and seeks related feedback on items to be captured in this Parking Lot.
Distribution Utility Review Process (Clause 292)
MISO has this on the calendar for Q4 2021 but MISO/Transmission/DERA/EDC Coordination
Suggested use cases that can be transparently evaluated by the DERTF.
We need more time to document these use cases.
Energy: Wind PPA
Energy: Solar Facility
Ancillary: Solar + ESS
Capacity: Solar + ESS
Existing DER case
New DER case
Same distribution circuit vs Same distribution substation (load EPnode)
Advanced Energy Management Alliance (“AEMA”) [1] respectfully submits the following comments to the MISO Distributed Energy Resource Task Force (“DERTF”) on the second iteration of the Order 2222 Filing Framework that was presented at the August 2, 2021, meeting of the DERTF.[2] AEMA is a trade association under Section 501(c)(6) of the Federal tax code whose members include national distributed energy resource companies and advanced energy management service and technology providers, including demand response (“DR”) providers, as well as some of the nation’s largest demand response and distributed energy resources. AEMA members support the beneficial incorporation of distributed energy resources (“DER” or “DERs”), including advanced energy management solutions, into wholesale markets as a means to achieving electricity cost savings for consumers, contributing to system reliability, and ensuring balanced price formation. These comments represent the collective consensus of AEMA as an organization, although they do not necessarily represent the individual positions of the full diversity of AEMA member companies.
AEMA appreciates MISO sharing the ongoing iterations of the comprehensive proposal to comply with FERC Order 2222. In the feedback request, MISO asked for comments on specific issues and the AEMA responses are as follows:
AEMA supports MISOs proposal to utilize the aggregated meter values for settlements. During the DERTF meeting, there was confusion expressed by stakeholders on slides 68-70 of the Compliance Framework presentation. The confusion centered on what is meant by metering at the “individual DER” level.[3] From the verbal discussion and the example on slide 70, it appears that MISO is proposing to receive a single meter value from aggregations of similar DER types, but not the individual DERs. MISO would then aggregate those meter values into a single value to determine aggregate performance. Since the DER Aggregator (DERA) has the capability of utilizing different DERs for meeting performance obligations, this process should be acceptable since the evaluation is not against the specific DER types.
Ultimately, AEMA recommends MISO require the DERA to only supply a single set of metered values for the load reduction and injection portions of each DERa of heterogeneous resources, as opposed to breaking out each individual resource type by homogeneous associations.
Whether MISO follows its current proposal, or simplifies the process as AEMA recommends, AEMA reiterates MISO should not require individual DER metering because it would be a substantial and costly barrier to participation of DERAs that provides no value to MISO operations. (For example, requiring meter values of each solar panel in a small solar farm or each thermostat from an aggregation of many thermostats).
On a separate topic, it is AEMA’s understanding that MISO is proposing to require Real Time (RT) telemetry at 2-second intervals at the aggregated level for aggregations of DER above 5 MWs or those providing Regulation service. AEMA requests MISO clarify that any RT telemetry requirement is requested at the aggregated level and will not be required at the individual DER level regardless of individual DER size. AEMA will reemphasize that the DERA
AEMA also requests MISO present a summary of the timing of settlement meter data. Specifically, when is the meter data due for specific settlement statements, and are the expectations from DERAs any different from all other market participants?
While AEMA recognizes the concept of creating a Parking Lot for capturing future work related to DER makes sense for certain issues, AEMA urges MISO to avoid using the Parking Lot as much as possible. For example, currently, some market processes, not technically feasible, should move to the Parking Lot until they are technically feasible (for example, after the Market System Enhancement (MSE) project is completed). MISO should create a process to revisit those project enhancements at that point in time as part of the compliance commitment to Order 2222.
MISO should not use the Parking Lot to hold items that could currently be implemented as part of the proposed compliance plan. Compliance with Order 2222 should pull in all as many options as are feasible during the initial project execution, when implementation costs would likely be at a minimum. Shifting enhancements to a parking lot could create future cost barriers to implementation if the enhancement. As AEMA mentioned in previous comments, there are elements of the MISO compliance proposal which limit the potential participation of DERAs in the MISO market. For example, limiting aggregation to a single CP node is a significant barrier to participation. MISO has not demonstrated that absolutely no level of aggregation or aggregation for limited-service offerings is technically infeasible.
Yes. Scan rates should be relaxed for non-regulation qualified, dispatchable resources, less than 5 MWs. This relaxation should be matched to services being provided and simple DER response should not have an ICCP requirement associated with them. Installing advanced, real-time metering at a 2-second interval can be costly and does not provide commensurate value to the MISO grid operator because resources of a few MWs are within the noise band of MISO operations. This is similar to some resources today, such as DRR Type I, which does not provide Real-Time telemetry.
Based on the timing requirements associated with registering and modeling in the MISO market, AEMA recommends MISO develop a timing calendar allowing for published data to be reviewed for utility load levels. This could be published EIA data or other publicly available data sources, presuming the data sources meet the Order 2222 requirement[4] that the data is based upon the utilities prior fiscal year’s data. In the event data for the prior fiscal year is not available to align with MISO’s registration, modeling, and other MISO auction timelines, then AEMA recommends MISO include in its compliance filing that the most recent publicly available data on a utility’s fiscal year sales be used for determining if a utility falls above or below the 4 million MWh threshold.
Once the data is published, a timeline for DERAs to secure approval from RERRAs regulating the identified utilities that have are found to be below the 4 million MWh threshold, registering and getting the resource into the market should be identified giving the DERA a full year of market participation. This may mean the participation calendar does not match the normal annual calendar.
For example, if data is published in March for the prior year and it takes 60 days for a resource to be registered, modeled, and begin participation in the market, then the participation year could run from June through May of the following year.
MISO should establish a process examining publicly available data, such as the EIA data, and then rely upon the DERA to certify the data at registration. The DU can examine the information for any concerns during their safety and reliability review. MISO should instruct the DU to notify them (and the DERA) if they anticipate load levels to fall below 4 mm MW-hrs.
MISO should suggest utilities seeking to “opt-in” align with the timeline stated above, where an “opt-in” lasts at least a year and gives time for registration and modeling before the clock begins. For example, MISO could establish a process allowing “opt in” on a quarterly basis, beginning at the next quarter and lasts for one calendar year from the start. Obviously, more details would need to be worked out, but this would be the basic principle for handling “opt-ins.”
MISO has shared several use cases and stated that they are looking at the AEE presentation and the work of EPRI for additional use case examples.[5] These examples will be very valuable in understanding how compliance with Order 2222 will work, from registration to settlements. AEMA encourages MISO to compile these cases mentioned in the MISO presentation and begin flushing out the details of those cases first.
AEMA appreciates MISO’s consideration of these comments as part of the Order 2222 compliance approach being discussed in the DERTF. We welcome any questions, and encourage you to contact either Katherine Hamilton, Executive Director of AEMA, or DeWayne Todd, representative of AEMA, should you wish to discuss with AEMA members.
Respectfully Submitted,
Katherine Hamilton
Executive Director, Advanced Energy Management Alliance
Katherine@aem-alliance.org
202-524-8832
or
DeWayne Todd
DDT LLC
dewaynetodd1297@gmail.com
812-573-8052
WPPI’s feedback on Iteration 2 of FERC Order 222 Filing Framework presented at the DERTF, 8/2 is as follows:
(1) Parking Lot: It makes sense to focus on what is necessary for compliance with O2x4 and leave refinements/enhancements to be worked later, depending on the level of participation of DER aggregations (DERas) in MISO markets and the priority of Parking Lot issues relative to other potential initiatives. WPPI does not have any issues to add to the Parking Lot.
(2) Scan rates: Scan rates should be relaxed for non-regulation, qualified, dispatchable resources less than 5 MW if such relaxed scan rates provide a material reduction in the burden on a DER Aggregator (DERA).
(3) Small utilities opt-in: It seems this would be best managed by utilities just above the 4M MWh opt-in threshold and their Relevant Electric Retail Rate Regulatory Authority. It may be an issue they will want to address in an agreement between the utility and the DERA.
(4) Use cases: At this time, WPPI does not have any specific DERas it is anticipating on our member distribution systems. However, we are very interested in exploring a variety of use cases in order to determine the data necessary to separate a DERa’s participation in MISO from a Load Serving Entity’s participation in MISO (namely, the LSE’s load purchases), as well as ensure a DER in a DERa does not use wholesale purchases at retail. To the extent a DERa’s participation in MISO can be directly metered (including metered and subject to measurement and verification as is the case with demand response), such separation is relatively straightforward. However, what data are necessary if a DERa includes one or more DERs that participate in retail program/s? Includes one or more DERs that have behind the retail meter solar and storage? (Just a couple of examples.)
Consumers Energy appreciates the opportunity to provide comments regarding the second iteration of MISO’s FERC Order 2222 Filing Framework Document
MISO’s proposal to create a ‘Parking Lot’ which will house issues that require further definition beyond the needs of the FERC Order 2222 compliance filing is one that Consumers Energy can support. It may ultimately make the compliance filing effort more efficient as well. There have been times when conversations at the DER meetings have gotten derailed on very nuanced or significantly technical points. With the creation of the Parking Lot, stakeholders can now be assured that even if their concern is not going to be addressed at a meeting, it will be captured in the Parking Lot and addressed at another time. Documenting these issues is vitally important so that we do not lose the thought leadership provided by the stakeholder community.
The scan rate requirement for non-regulation qualified dispatchable resources needs to be based on the market services provided and should require the most stringent of (i) MISO requirements; (ii) State interconnection requirements; and (iii) Electric Distribution Company (EDC) requirements.
As anticipated by the question , the minimum opt-in tenure should be one year and should track the Planning Year (PY) schedule (currently June – May). This question illustrates why it is important to have the exact same set of rules for large distribution utilities required to comply with FERC Order 2222 and for small utilities choosing to opt-in to the FERC Order 2222 requirements. This way, if a utility toggles back and forth between a small and a large designation, there is no need for anyone to do anything special or out of the ordinary. The same processes and procedures can be followed and all parties (distribution utility, transmission owner, MISO, RERRA) can simply maintain their existing rights and obligations. Such a construct is not only easier to manage and administer, but it will also allow smaller utilities to offer programs that are greater than one year in duration, which is something desired by certain customer segments. It would be difficult, if not impossible, for utilities bordering small/large status to offer multi-year programs if it feared that it would need to comply with two potentially different sets of rules from year to year. Keeping one set of rules for all utilities, whether complying mandatorily or voluntarily with FERC Order 2222, provides the end-use customer with the greatest set of alternatives.
Verification rules should be the same for large utilities that are required to comply with FERC Order 2222 and for small utilities that choose to opt-in to the requirements of FERC Order 2222. These rules should remain the same for all parties involved, namely the distribution utility, the transmission company, MISO and the RERRA. Creating a second set of ‘special’ rules solely for the small utilities not only has the potential to cause confusion and errors, but will also shift additional burdens onto the remaining players (large distribution utilities, transmission owners, MISO, RERRA) as these parties will need to assume any verification responsibilities that should be assigned to the small distribution utility.
As noted above, the minimum opt-in tenure should be one year and should track the Planning Year (PY) schedule (currently June – May). Implementation of FERC Order 2222 is already going to require significant changes to existing processes and procedures. The industry does not need to further complicate matters by creating special rules, be they about time periods or anything else, for small utilities that opt-in. One set of rules for all utilities will suffice and, as noted above, will also be to the benefit of customers.
Consumers Energy has no suggested use cases at this time.
Once again, thank you for providing the opportunity to provide comments on this issue.
Voltus Comments to MISO Aug 2, 2021 DERTF Feedback Request
DERTF Feedback Requested on Filing Framework Document – Iteration 2 (IR070)
MISO requested stakeholder feedback on the following:
Voltus appreciates MISO's intent behind the Parking Lot for placing any future additional work so that the FERC Compliance Filing timeline is not impacted. However, Voltus cautions MISO that the MISO Parking Lot should not be a place to defer items, which could be worked via the DERTF pro-actively to meet the FERC Order 2222 compliance requirements.
For example, MISO currently has Demand Response Resource (DRR) Type I and II market participation models for demand response programs. We don't see any need for MISO to place DRR improvements in the parking lot when MISO could take active steps towards making DRR compliant for O2222 requirements.
Another example would be the interconnection requirements. Several stakeholders in Interconnection Planning Working Group, Distribution Utility Coordination meetings, and the DERTF have asked MISO to discuss interconnection requirements sooner than putting them off after the compliance filing.
Voltus answers "yes," telemetry requirements should be relaxed for non-regulation resources (regardless of their size).
As mentioned in slide 9 of Voltus May 10, 2021, MISO DERTF presentation, we propose MISO match metering granularity and telemetry requirements to services offered by the Aggregated DER. This proposed approach would be consistent with the current MISO practice of requiring hourly data from MISO capacity market participants and 5-min data from DRR Type I resources providing reserves in the ancillary services market. Hence telemetry requirements should be relaxed for non-regulation resources regardless of their size.
a) What about utilities that may fall above the line in one fiscal year and below the line the next year?
b) Who is responsible for verifying this data?
c) For those utilities which opt-in, over what period of time is that opt-in "authorized"? How does this align with MISO process timelines?
Voltus believes RERRAs should be able to determine the duration of their opt-ins and scope those opt-ins as they see fit. RERRAs should be able to limit opt-ins to apply to particular resources participating in particular market programs or products.
Voltus proposes 3 use cases that demonstrate:
Voltus Use case 1 - Use existing baselines established for demand response programs for all DERs.
In use case 1, presented on May 10, 2021, MISO DERTF meeting, the consumption baseline—as calculated for existing DR resources--is established at a positive 10 MW. Load of the DER is 5 MW in Interval 1, 0 MW in Interval 2, -5 MW in Interval 3, and -10 MW in Interval 4. Negative load implies the DER is injecting load to the grid.
Table 1: Voltus Use case 1 - Use existing baselines established for demand response programs for all DERs
Performance | Interval 1 | Interval 2 | Interval 3 | Interval 4 |
Consumption Baseline | 10 MW | 10 MW | 10 MW | 10 MW |
Actual Load | 5 MW | 0 MW | Negative 5 MW | Negative 10 MW |
This use case illustrates that the existing baselines established for demand response programs can measure both curtailment and injection. The two—curtailment vs. injection—can be distinguished for purposes of applying FERC Order 745’s Net Benefits test, as curtailment is reflected in performance between the baseline and 0 load while injection is reflected as performance below the x axis.
Figure 1: Voltus Use case 1 - Use existing baselines established for demand response programs for all DERs
Voltus Use case 2 - Established DR M&V can be used for a single DER with multiple underlying technologies & one point of metering
In use case 2, within a single facility there are multiple technologies such as a DR resource, a generator, and an energy storage device. Despite the complex mix of technologies contributing to the DER’s performance, the exact same M&V as seen in use case 1 can apply because the technologies share a single metering point.
Table 2: Voltus Use case 2 - Established DR M&V can be used for a single DER with multiple underlying technologies & one point of metering
Performance | Interval 1 | Interval 2 | Interval 3 | Interval 4 |
Consumption Baseline (A) | 10 MW | 10 MW | 10 MW | 10 MW |
Load Curtailment (B) | 5 MW | 5 MW |
|
|
Generation (C) |
|
| 10 MW | 15 MW |
Energy Storage (D) |
| 5 MW | 5 MW | 5 MW |
Actual Load = A-B-C-D | 5 MW | 0 MW | Negative 5 MW | Negative 10 MW |
This particular use case 2 illustrates how a single facility with multiple technologies can function as one DER with a single point of metering. There is no need for the M&V to account for this performance by looking at each individual technology because the net impact to the grid is identical to use case 1.
Figure 2: Voltus Use case 2 - Established DR M&V can be used for a single DER with multiple underlying technologies & one point of metering
Voltus Use case 3 - Established DR M&V can be used for an aggregation of many DERs with varying underlying technologies.
Use case 3 shows an aggregation of different DERs with varying underlying technologies such as solar and diesel generators in addition to curtailable loads. There are 4 individual DERs in this use case, some of which provide grid services by reducing grid demand relative to a baseline and some of which respond to dispatch instructions by increasing generation. The graphic illustrates that the aggregate performance is the sum of individual DER performances.
The consumption baseline in Curtailable Load 1 DER is established at 10 MW, similar to the existing DR program example in Voltus Use Case 1. And the performance of the DR program was 8 MW in Interval 1, 6 MW in Interval 2, 4 MW in Interval 3, and 2 MW in Interval 4.
In Curtailable Load 2 DER, the consumption baseline varies according to the interval. For this curtailable load 2, the baseline is 5 MW in Interval 1, 4 MW in Interval 2, 6 MW in Interval 3, and 5 MW in Interval 4. And the performance of the DR program was 3 MW in Interval 1, 2 MW in Interval 2, 5 MW in Interval 3, and 1 MW in Interval 4.
In Solar Array DER, the solar array generation output varies by interval. In Interval 1, the solar output is 5 MW. In Interval 2, the output is 6 MW, and Intervals 3 and 4 stay constant at 8 MW.
And finally, in the Diesel Generator DER, the diesel generator's output is a constant 2 MW for 4 Intervals.
Table 3: Voltus Use case 3 - Established DR M&V can be used for an aggregation of many DERs with varying underlying technologies
Performance | Interval 1 | Interval 2 | Interval 3 | Interval 4 |
Curtailable Load 1 DER | ||||
Consumption Baseline | 10 MW | 10 MW | 10 MW | 10 MW |
Actual Load | 8 MW | 6 MW | 4 MW | 2 MW |
Curtailable Load 2 DER | ||||
Consumption Baseline | 5 MW | 4 MW | 6 MW | 5 MW |
Actual Load | 3 MW | 2 MW | 5 MW | 1 MW |
Solar Array DER #3 | ||||
Actual Output | 5 MW | 6 MW | 8 MW | 8 MW |
Diesel Generator DER #4 | ||||
Actual Output | 2 MW | 2 MW | 2 MW | 2 MW |
This particular use case 3 illustrates that the aggregate performance is the sum of individual DER performance regardless of if that performance if achieved through curtailment or injection.
Figure 3: Voltus Use case 3 - Established DR M&V can be used for an aggregation of many DERs with varying underlying technologies