MISO is requesting feedback on posted Proposed Technical Screening Criteria.
Please provide feedback by May 2, 2022.
Transmission Owner Sector Feedback on Proposed Technical Screening Criteria presented at the April 11, 2022 Meeting of the Interconnection Process Working Group
May 2, 2022
The MISO Transmission Owners (Owners or TOs) appreciate the opportunity to comment on Proposed Technical Screening Criteria for Distributed Energy Resources and Distributed Energy Resource Aggregations presented by MISO at the April 11, 2022 Meeting of the Interconnection Process Working Group (IPWG), and provide the feedback below for MISO’s consideration.
Do the proposed screens accurately capture potential transmission system reliability impacts?
Owners are concerned with MISO’s proposal to use summer peak load for screening rather than off-peak load for both the TO and MISO screens. Owners would prefer that the evaluation of impact of an interconnecting DER or collection of interconnected DERs be determined at shoulder peak or at both shoulder and peak.
Are there gaps in the coverage of the proposed technical screens (i.e., false negative outcome)?
Are there alternative screening criteria that should be evaluated?
if impact is identified by the Owner, MISO should perform a study. TOs need flexibility in identifying the potential need for upgrades due to the impact of a DER interconnections.
MISO’s proposed 1% line loading change screen
A 1% line-loading change screen is reasonable as a starting threshold, but only up to a 1MW impact. For example, DER could impact the transmission system up to 1 MW (1 MVA) without MISO involvement, but If DER exceeded the 1 MW threshold, then the 1% rule would apply.
General Feedback
Timeline of MISO/TO Study process should be coordinated with respective State DER Interconnection process and timeline.
Please provide clarification about peak load at the substation used for the threshold criteria whether the peak load is the Net load that accounts for all existing interconnected DER offsetting the load at the substation. There can be higher level of power injection to the transmission system when Distribution substation load is at minimum load.
• Are there gaps in the coverage of the proposed technical screens (i.e., false negative
outcome)?
The threshold for Power injection to the Transmission System should be looked at minimum load at substation, but not at peak load. The power injection due to DER at peak load can be lower than during minimum load. Please clarify the definition of peak load to make sure projects screening for transmission Study is accurate.
ITC Holdings thanks MISO for the opportunity to comment on the Proposed Technical Screening Criteria for DER Interconnection Requests discussed at the IPWG.
ITC has the following comments regarding the 5 MW Power Injection Criteria MISO has proposed. While typically this criterion of 5 MW at peak will suffice to identify areas of concern for power injection into the transmission system there are a couple of conditions that could cause concerns with this criterion.
The proposed screens, >= 5 MW injected onto the transmission system at peak AND >= 1% of Summer rating change in line flow, which are based on and similar to standard Affected System impact criteria, provide a useful starting point for discussion. In response to MISO’s specific questions, these appear practical to implement and have no specific problems obvious to us beyond what we note below.
We do have some concerns. In particular, it’s not clear to us that peak-demand models provide the appropriate basis for evaluating DER impacts. A 5 MW injection during peak conditions may correspond to a much larger injection during other conditions that prevail during many hours of the year. If such injections were to occur at multiple points within a given area, very significant impacts could result, and MISO’s proposal does not appear to provide assurance that such impacts could be managed.
Finally, we note our understanding that the Affected System are applied by MISO as OR criteria—that is satisfaction of any one element would trigger the screen—while MISO proposes to apply the two criteria in question on an AND basis—so that both would have to be satisfied to trigger the screen. To the extent that MISO proposes these criteria in order to achieve some consistency with Affected System study criteria, this change to AND logic represents a departure.
SunEnergy1 supports the criteria proposed by MISO. It is consistent with screening criteria used on other affected systems. It also strikes a balance between ensuring system reliability and reasonable study efforts. Two things to clarify in future languages 1) Clarify that criteria are to be applied to the aggregate impact of DERs to be studied, not individual DERs. 2) Need future design when the distribution line is not radially connect to a single transmission substation -- the distribution lines are networked.
Thank you the opportunity of providing feedback.
Kun