MISO is requesting feedback on Proposed IBR Performance Requirements.
Please provide feedback by July 14, 2023.
AES Clean Energy appreciates the opportunity to provide feedback on MISO’s proposed implementation of specific clauses of IEEE 2800 standard, and offers the following responses to MISO’s specific technical questions:
1.What is the preferred default setting for enter service intentional adjustable minimum delay and duration of enter service period? (Slide 9)
AES Clean Energy does not oppose the default settings proposed by MISO for enter service criteria. These values align with our current operational practices.
2. What specific concerns, if any, could arise from MISO’s proposal to define the Reference Point of Applicability (RPA) as the Point of Interconnection (POI)?
AES Clean Energy does not oppose the RPA as the POI but recommends that the RPA be more specifically defined as the high side of the GSU, which would make it easier for generators to comply with these standards.
3. MISO’s proposal to implement the Tariff changes for GIA’s resulting from DPP-2022-Cycle interconnection requests
AES Clean Energy does not oppose MISO’s decision to implement these changes on a forward basis and is optimistic that projects in DPP-2022-cycle should have sufficient time to become compliant with the new standards. AES Clean Energy expects projects in this cycle to reach COD between 2027-2029, which should be a sufficient runway. However, AES Clean Energy recommends that MISO offer some flexibility to delay implementation if generator owners are able to provide sufficient evidence that equipment manufactures do not offer products that are IEEE 2800 compliant.
Clean Grid Alliance Comments on Inverter Based Resource Requirements
July 14, 2023
Clean Grid Alliance appreciates the opportunity to provide feedback to MISO on the proposed IBR requirements.
Timing of Implementation:
Several actions should be completed prior to implementation of new IBR requirements:
The timing of the implementation of any new policy or standard is an important factor to consider. For example, if MISO implements a new IBR standard and none of the IBR manufacturers (or only a select few) are able to meet them, it will have significant impacts on the MISO market including preventing viable/ready projects from reaching COD. Stakeholders are looking to MISO for guidance in sharing a publicly available document demonstrating that a majority of IBR manufacturers can meet the new standards, to ensure that MISO itself will not be preventing generation interconnection projects from reaching COD by implementing policy that cannot be met.
Additionally, new IBR requirements should only be implemented in forward DPP cycles, as projects currently queued up in the DPP 2022 cycle have already submitted engineering models and would face material modification and potentially supply issues in trying to change equipment after studies have officially been kicked off. New standards should be implemented with sufficient notice prior to a DPP queue cycle closing to similarly avoid market impacts and additional administrative burdens on MISO staff.
Finally, implementation of new IBR requirements should be planned for after finalization of the IEEE 2800.2 standard for testing and verification. Otherwise, there will be issues with consistency among individual projects, particularly around self-certification and collection of operational data.
Sincerely,
Rhonda Peters, Ph.D.
Technical Consultant for Clean Grid Alliance
NG Renewables notes that the IEEE 2800 has not been finalized, and that changes developed during this stakeholder process should not be applied until it is officially adopted. Therefore, the enter service criteria time should remain consistent with PRC24-002 until that time.
NG Renewables also agrees that the Point of measurement or Point of Monitoring is the most appropriate place to locate the reference point of applicability (RPA). However, it would be helpful if MISO could clarify some of the elements in the IEEE 2800 diagram presented, specifically what a “supplemental IBR device” would mean in a MISO context.
Transmission Owner Feedback on Inverter-Based Resource Performance Requirements Proposed to IPWG
IPWG: Proposed IBR Performance Requirements (20230620)
July 14, 2023
In the June 20, 2023, meeting of the Interconnection Process Working Group (IPWG), stakeholders were invited to submit feedback on:
Responses to MISO’s questions:
Proposed changes to MISO’s draft Generator Interconnection Agreement (GIA) Tariff redline language
Specific input on the following technical questions:
MISO’s proposal to implement the Tariff changes for GIA’s resulting from DPP-2022-Cycle interconnection requests
In conjunction with implementation of these IBR requirements, MISO should perform:
MISO should indicate in Appendix G that TO-specific IBR requirements which are more stringent will supersede.
IEEE2800 is to improve the reliability of IBR plants in weak grids so exceptions that may negatively impact reliability need to be considered carefully. MISO has included IEEE2800, section 7.2.2.6 “Restore output after voltage ride-through” (provided below for reference) provides for exceptions to the IBR performance requirements established in the standard and is included in the list of requirements for implementation with this proposed revision.
“Weak Grid” areas are areas of the system that do not have sufficient synchronous generation such that any change of real or reactive power can lead to large swings of angle and voltage. Short circuit ratio is the primary consideration in identifying weak grid locations.
IBRs that connect to Weak Grids may not be able to provide either fast frequency response or fast voltage control because doing so may lead to IBR control instability and cause protection mis-operations on transmission facilities. For this reason, IEEE2800, section 7.2.2.6 “Restore output after voltage ride-through” allows for exceptions to some IBR requirements to achieve reliable transmission system operations and avoid the impacts that could result from the IBR performing according to the standard.
In weak grid areas, IBR response requirements will need to be evaluated on a case-by-case basis. Recommend that MISO work with Transmission Planners to establish a generic definition for Weak Grid but allow for TOs to provide their own definitions in their LPC, reflective of their own system’s conditions and the characteristics of the interconnecting resource(s).
IEEE2800, section 7.2.2.6 “Restore output after voltage ride-through”
The active power recovery time shall be configurable within a range between 1.0 s and 10 s. The default active power recovery time is 1 s; however, in weak grids, in order to reduce oscillatory behavior of the IBR plant upon fault recovery and maintain system stability, it may be desirable to reduce the average rate of active power recovery in consultation with the TS owner. Any modification of the recovery time from the default value shall be based on a mutual agreement between the IBR owner and the TS owner. The time to restore active power output shall be a target time with a tolerance that is the greater of ± 0.2 s or ± 10% of configured active power recovery time in seconds and shall not be interpreted as a maximum time.
July 14, 2023
Apex Clean Energy appreciates the opportunity to provide MISO feedback on the IPWG: Proposed IBR Performance Requirements.
NextEra Energy (NextEra) appreciates the opportunity to comment on MISO’s efforts to improve the grid reliability through implementing IEEE 2800 Inverter-Based Resource (IBR) Performance Requirements. NextEra is aware of Original Equipment Manufacturer (OEM) comments submitted to other ISOs regarding the adaptation of the IEEE 2800 standards indicating the need for significant engineering effort to update the current products into compliance. For that reason, we urge MISO to consider that the requirements be applicable to projects in DPP 2023 and beyond.
Key comments/questions/recommendations from NextEra about MISO Interconnection Process Working Group's (IPWG) proposed IBR Performance Requirements:
Technical Feedback:
Based on industry feedback, a 10 mS requirement is recommended instead of 1 ms for data synchronization.
NextEra recommends MISO reach out to OEMs for better feedback on these requirements including the time durations for enter service.