In the March 10, 2023, Long Range Transmission Planning (LRTP) Workshop, an update was provided on the MISO Futures refresh including Future 2A final expansion and preliminary siting. Feedback is requested on the preliminary F2A siting results, specifically siting locations and amounts with respect to a site's feasibility to interconnect the respective resource. If a site is not feasible, please provide an alternative site.
Feedback may be provided in two forms: directly through the Feedback Tool (narrative) and separately via spreadsheet (siting data). Spreadsheets should be submitted to Stakeholder Relations with specification as to whether it should be posted (public) or not posted (confidential).
All feedback is due by March 24.
The Municipals, Cooperatives and Transmission Dependent Utilities (“TDU”) Sector in December 2022 submitted comments raising concerns with draft expansion plan information provided by MISO. In reviewing expansion plan information provided in March 2023 it does not appear that MISO has made material changes in response to the feedback from the Sector. The TDU Sector is once again submitting its concerns with the draft expansion plan and asks that these be addressed. In addition, members of the sector have identified area specific issues with the draft expansion plan and will be providing separate comments with those issues to MISO. Overall, it appears that it will be challenging to site all of the new resources currently being added as part of Future 2a. Given this, as well as the general and specific concerns the Sector has with the expansion plan, the Sector requests that MISO provide updated expansion plan information reflecting feedback received and that another opportunity be provided for stakeholders to comment on the updated information. The TDU Sector feels the importance of the expansion plan to LRTP planning is worth taking additional time to help ensure information used is reasonable.
Provided below are the TDU Sector’s initial thoughts submitted in December 2022 on MISO’s draft Futures F2A expansion results. As noted above, the sector asks MISO to address these concerns. The sector appreciates MISO’s efforts on this aspect of the planning and overall continues to be supportive of the LRTP effort. We look forward to continued discussion with MISO on this work.
Currently, ICC staff does not have any direct input Future 2A’s siting recommendations. However, ICC staff does want to express appreciation for the Future 2A update. It is reasonable to update Future assumptions with changes in generation development and retirements, especially as a result of public policy like the Illinois Climate and Equitable Jobs Act (CEJA). ICC staff also asks MISO to report any other state agencies, beyond public utility commissions, are being consulted on siting issues.
ICC staff is curious about whether load changes will be included in upcoming Futures updates. Much as public policy is shaping retirements and generation, policy could also potentially impact load. Public policies addressing energy efficiency, building electrification, and EVs are increasingly common. Further, outside of public policy, changes in industry – notably the growth of data centers – might also impact load predictions going forward. Given these trends, are there any plans to update load predictions as part of any forthcoming Future updates?
ICC staff is also encouraged by MISO’s consideration of HVDC lines in its Tranche 2 planning. HVDC lines offer a number of benefits, including moving power efficiently over long distances with lower losses and without the need for reactive power consumption. HVDC lines will be an important tool in moving resources from renewable rich zones to load centers. At the same time, ICC staff also supports MISO’s “all things considered” approach to transmission planning. HVDC might not be right in all contexts, and considering a range of line options to address cost, land use, and contingency concerns is a good approach.
Finally, ICC staff would like more information the impact the additional siting proposed in Future 2A will have on the MISO queue. Will these additional resources be able to clear the queue in a timely manner, to meet state policy goals?
WEC Energy Group submits the following comments in response to MISO's request for feedback on the Future 2A resource expansion and siting. One item in particular raised immediate concern – the amount of DR for both Wisconsin Public Service (WPSC) and Wisconsin Electric (WE) is nearly 300 MW each in Year 5. This amount of DR is not consistent with our internal studies which are not picking DR in our expansion plan (especially by Year 5). We note that other LSEs in LRZ 2 have little to no DR in the Future 2A expansion plan through the 20 year study period. All LSEs in LRZ 2 should have relatively comparable DR in the Future 2A expansion plans and as noted above, our internal studies are not picking DR.
We also note that the amount of RRF wind units in LRZ 2 (WI/Upper MI) is over 5 GW through Year 20. We do not believe that LRZ 2 can accommodate this amount of wind. In comparison, the amount of RRF solar and solar hybrid in LRZ 2 is only 2 GW through Year 20. We would have expected just the opposite – more solar than wind in LRZ 2. Despite MISO assumptions regarding the enhanced production tax credit of wind when compared to solar, the 2022 generation interconnection queue shows solar resources outpaces wind resources at about 86% (84 GW) of the 98 GW of wind and solar in that queue. The TDU Sector made similar observations in their Dec 16, 2022 feedback on Future 2A. As we requested in LRTP Tranche 1, MISO should, at the very least, perform sensitivity studies with more solar to determine the effectiveness of the Tranche 2 transmission expansion plan.
We are glad to see aggressive capacity expansions especially renewables in Future 2A. There however does appear to be vast differences among the Local Resource Zones (LRZs) regarding their respective capacity expansions. Why are we seeing such large differences between neighboring LRZ’s? An example of this can be seen between LRZ 1 and LRZ 2.
Thank you.
Otter Tail Power Company (OTP) appreciates the opportunity to provide comments on MISO’s preliminary Future 2A siting results. Developing credible Futures is an important part of the LRTP effort to ensure that the final Tranche 2 portfolio of transmission projects is cost effective and can maintain grid reliability.
OTP has several general comments on the preliminary siting results and will also provide more specific comments on the future generators in OTP’s area in the siting spreadsheet.
The Formal Feedback of the Mississippi Public Service Commission regarding Future 2A Expansion and Preliminary Siting (20230310) was submitted as a PDF attachment via email to stakeholderrelations@misoenergy.org. That email and attachment may be viewed by the public.
Minnesota Power is seeking to more clearly understand the Futures 2A portfolio for both the energy adequacy - hourly resource/load understanding, and the resource adequacy attributes.
North Dakota appreciates the opportunity to provide comments on MISO’s preliminary Future 2A siting results. The assumptions MISO uses in modeling these futures are a significant driver of new transmission projects. According to the current tariff on file, these transmission lines are paid on a postage stamp basis by all MISO North customers. Therefore, MISO must make every effort to spread these investments fairly throughout the region. This is especially true since the next tranche will naturally reflect the need for more transmission in states with high decarbonation goal and customers in states with lower decarbonization goals will then be subsidizing those policies.
Overall, the assumptions for future generation being siting and developed in North Dakota are extremely light and fail to recognize a couple important realities:
1) North Dakota is the only natural gas producing state in the MISO region making it an extremely valuable and logical place to assume development of additional natural gas peaking units. These will be essential for reliable operations into the indefinite future, and North Dakota’s in-state production offers fuel security that all other locations lack. What's more, one such facility that is already planned by Xcel in North Dakota is not even reflected in this refresh.
2) North Dakota has one of the best wind resources in the MISO region, which enhances the reliability, reduces intermittency, and increases the efficiency of wind generators in North Dakota. MISO needs to increase the assumption for wind development in North Dakota.
North Dakota is also concerned with the lack of dispatchable power MISO assumes will be developed in this model. Dispatchable resources, even if they aren’t being planned by MISO utilities, need to be modeled in order to reflect a system that is reliable longterm and has the transmission infrastructure needed to support this essential generation.
Additionally, we echo the concerns raised by Otter Tail Power, MDU and Xcel, specifically:
The lack of siting MISO is reflecting in the MDU territory is a real concern. MDU is on the western edge of the MISO region and serves load all the way into Montana. MDU is in the heart of the Bakken oil and gas field, making it a natural and valuable location for siting future natural gas generation. Additionally, the wind resources in central and western North Dakota are strong and MISO must not strand the potential of these resources by failing to enhance the transmission infrastructure there.
Invenergy thanks MISO for the opportunity to provide feedback on the draft Futures 2A siting results.
Invenergy appreciates the balance between certainty and extrapolation necessary to create pragmatic Futures scenarios. MISO’s Futures Initiative is lauded as a set of best practices in transmission planning process for the careful yet proactive consideration of need.
In the spirit of building upon this pursuit of balance, Invenergy would point towards inconsistencies in these assumptions which undermine this thoughtful intent.
Invenergy urges MISO to reconcile the treatment of state goals and IRPs with advanced, late-stage projects of the scale of the Grainbelt Express interregional MHVDC project.
MISO has held an executed GIA as the standard for generation to be modeled in a Futures scenario.While Invenergy sympathizes with the need for a certainty threshold for generation projects, the benchmarks for certainty between state IRPs and generation projects are hardly comparable. Grainbelt Express has only continued to advance through milestones since the previous Futures study. The project now has permits across all states, has been included in multiple state planning initiatives, and will execute its GIA a year before Tranche 2 is scheduled to be approved by the Board.
Meanwhile, MISO’s Future 2A scenario classifies a 2500 MW injection of offshore wind for which the BOEM lease has not yet taken place as a “committed” resource due to a commitment on paper.
Failing to consider a line with large future impacts on energy flows in the region risks exposing ratepayers to higher rates from energy prices and backbone buildout. Invenergy maintains that analyzing the potential impact of the Grainbelt project is consistent with the intent of MISO’s extensive Futures studies.
Invenergy respectfully requests that MISO model a 2500 MW injection into LRZ 5in the Futures 2A scenario to model the impact of Grainbelt. Invenergy would also ask that any impacts to the proposed Futures siting, or lack thereof, be presented at the next technical workshop.
Invenergy thanks MISO staff for their time and consideration.
Xcel Energy appreciates the opportunity to provide feedback on the draft siting results for the updated Future 2A. We feel that proactive planning efforts, like the LRTP, are an important piece of a safe, reliable, and affordable transition to a clean energy future, requiring a high degree of attention and coordination to achieve the goals of this transition. Xcel Energy remains open, and strongly encourages MISO staff to increase the coordination with the utilities in their footprint as these companies provide invaluable expertise in the areas they serve and ensure company plans are captured correctly. Xcel Energy submits the attached spreadsheet with suggested relocation of natural gas fired resources being sited within the State of Minnesota. While we don’t feel locating these resources within the Minnesota state borders is in direct conflict with the requirements adopted in recent clean energy legislation in the state, assuming these resources can receive approval to be constructed in the state is no longer a reasonable assumption. In addition, we feel that maximizing use of existing clean energy resources, such as existing nuclear generation, needs to be leveraged to its fullest extent and recommend reversing the assumed retirement of two nuclear generation units in the NSP footprint.
Maximizing use of existing infrastructure can also be applied to the fuel supply of natural gas fired resources. We feel any new natural gas fired generation should be done in such a way that minimizes the need for significant expansion of pipelines and minimizes difference on the transmission system that would result in a different energy source being utilized to fill the need of the assumed natural gas fired resources in the Futures.
In general, Xcel Energy is also concerned about the siting of renewable resources in the Arrowhead region of Minnesota. This area includes large areas or tribal lands and protected forests that make the siting of such resources difficult, at best. This area has also been found to be a lower value area for the development of renewable resources, having lower average wind speeds and solar irradiance than other areas. Because of these risks and inefficiencies, we recommend MISO work with the local utilities to find higher value resource locations for the renewables in Minnesota’s Arrowhead region, such as central and eastern North Dakota.
Finally, we feel strongly that local plans should be fully incorporated into these model updates to ensure the results of any analysis using these models are reasonable. Xcel Energy has recently filed a Certificate of Need application with the Minnesota Public Utilities Commission (MN PUC Docket # E002/CN22-131) to construct a generator tie line to allow our existing coal generation at in Sherburne County, MN to be replaced primarily with renewables. Failing to incorporate this plan into Future 2A will result in an unreasonable set of models, and any project that is developed from these models would face increased scrutiny and delay resulting from inaccurate assumptions.
Xcel Energy appreciates the efforts undertaken by MISO Staff to update the Futures and stand ready to provide assistance in any way MISO staff would need.
CT_COM_NSP_2026_1 | CTNSP26_ | Gas | Northern States Power Company | LRZ 01 | Minnesota | Yellow Medicine County | 231.8 | 231.8 | 231.8 | 231.8 | CT Gas | Committed | 601054 | No | 601006 (Split Rock 345 kV) |
CT_COM_NSP_2027_1 | CTNSP27_ | Gas | Northern States Power Company | LRZ 01 | Minnesota | Nicollet County | 374 | 374 | 374 | 374 | CT Gas | Committed | 603004 | No | 601006 (Split Rock 345 kV) |
CT_COM_NSP_2029_1 | CTNSP29_ | Gas | Northern States Power Company | LRZ 01 | Minnesota | Chisago County | 0 | 374 | 374 | 374 | CT Gas | Committed | 601018 | No | 602030 or 602031 (Wheaton) |
CT_COM_NSP_2030_1 | CTNSP30_ | Gas | Northern States Power Company | LRZ 01 | Minnesota | Roseau County | 0 | 374 | 374 | 374 | CT Gas | Committed | 602013 | No | 601067 (Bison 345 kV) |
CT_COM_NSP_2032_1 | CTNSP32_ | Gas | Northern States Power Company | LRZ 01 | Wisconsin | Eau Claire County | 0 | 374 | 374 | 374 | CT Gas | Committed | 605347 | Yes | |
CT_COM_NSP_2033_1 | CTNSP33_ | Gas | Northern States Power Company | LRZ 01 | Minnesota | Goodhue County | 0 | 0 | 748 | 748 | CT Gas | Committed | 601003 | No | Keep as Nuclear |
CT_COM_NSP_2034_1 | CTNSP34_ | Gas | Northern States Power Company | LRZ 01 | Minnesota | Jackson County | 0 | 0 | 374 | 374 | CT Gas | Committed | 601029 | No | 601006 (Split Rock 345 kV) |
CT_COM_NSP_2039_1 | CTNSP39_ | Gas | Northern States Power Company | LRZ 01 | Minnesota | Hennepin County | 0 | 0 | 0 | 374 | CT Gas | Committed | 601022 | No | 601031 (Brookings 345 kV) |
CTBLKST_COM_NSP_2025_1 | CTBLKS25 | Gas | Northern States Power Company | LRZ 01 | Minnesota | Hennepin County | 60 | 60 | 60 | 60 | CT Gas | Committed | 601024 | No | 601006 (Split Rock 345 kV) |
CTBLKST_COM_NSP_2026_1 | CTBLKS26 | Gas | Northern States Power Company | LRZ 01 | Minnesota | Hennepin County | 27 | 27 | 27 | 27 | CT Gas | Committed | 603095 | No | 601031 (Brookings 345 kV) |
WPPI notes potential issues with a limited number of sites in Wisconsin and Upper Michigan as indicated below. We would find it helpful if MISO included Bus Name and Bus kV fields in future postings as they provide more accessible information than bus numbers alone.
Finally, we are participating in separate comments to be submitted by our Muni/Co-op/TDU Sector.
Description Short Name Category LBA/Area LRZ State County Y15 MW Y20 MW Detailed Category Source Bus# Site Available for Use (Yes/No) Replacment Site Bus Number
RRF MISO F2A RW: MGE - 1 MGERW1 Wind Madison Gas and Electric Company LRZ 02 Wisconsin Sauk County 189 311 Wind RRF 694099 Identified bus is in Dane Co., ~12 miles and across a major river from Sauk Co.
RRF MISO F2A BATT: ALTE - 1 ALTEBT1 Battery Alliant East - Wisconsin Power and Light Company LRZ 02 Wisconsin Columbia County 75 75 Storage Battery RRF 693885 Very large injection for 69 kV system
RRF MISO F2A BATT: WPS - 2 WPSBT2 Battery Wisconsin Public Service Corporation LRZ 02 Wisconsin Manitowoc County 200 250 Storage Battery RRF 698590 Battery this size is too large for this single location
RRF MISO F2A BATT: ALTE - 3 ALTEBT3 Battery Alliant East - Wisconsin Power and Light Company LRZ 02 Wisconsin Columbia County 100 150 Storage Battery RRF 698201 Battery this size should be connected to adjacent 138 kV bus
RRF MISO F2A BATT: DPC - 1 DPCBT1 Battery Dairyland Power Cooperative (GSE) LRZ 01 Wisconsin Buffalo County 100 150 Storage Battery RRF 680173 Battery this size should be connected to adjacent 161 kV bus
RRF MISO F2A Wind: ALTE - 1 ALTEWD1 Wind Alliant East - Wisconsin Power and Light Company LRZ 02 Wisconsin Iowa County 250 250 Wind RRF 698016 Will cause large overloads at interconnection point
RRF MISO F2A Wind: NSP - 1 NSPWD1 Wind Northern States Power Company LRZ 01 Wisconsin Clark County 800 800 Wind RRF 603152 Will cause large overloads at interconnection point
Grant County GRANTCOP Solar Alliant East - Wisconsin Power and Light Company LRZ 02 Wisconsin Rock County 200 200 Solar PV Committed 693478 Capacity very high for 69 kV interconnection
RRF MISO F2A Wind: WEC - 2 WECWD2 Wind Wisconsin Electric Power Company LRZ 02 Wisconsin Waukesha County 510 510 Wind RRF 699247 This is an aggressive MW target for this site, with urban/suburban development on 3 sides, and modest wind resource
RRF MISO F2A Wind: WPS - 2 WPSWD2 Wind Wisconsin Public Service Corporation LRZ 02 Wisconsin Marathon County 539 539 Wind RRF 699676 This is an aggressive MW target for this site, with lots of river valley and forest nearby, and modest wind resource
DTE appreciates the opportunity to provide input on the preliminary Future 2A siting results. Upon review of the worksheets that contain the additions, retirements, and the siting we have the following concerns:
Again, we recommend that MISO reevaluate their assumptions on age based retirements for originally installed wind sites and consider recategorizing them as “Out of Study Period” to account for situations where they could be re-powered or replaced. Additionally, MISO should keep large gas peakers in the case studies through the 2042 (Y20) study period. MISO should also update the retirement schedules so that they are consistent with the most recent IRP plans submitted by stakeholders. There seems to be significant misalignment which will skew the analysis of transmission needs. Lastly, we recommend that MISO reference the bus locations that were submitted by stakeholders for the wind and solar category to ensure the correct POI are utilized in the preliminary siting for F2A.
Entergy Response to MISO Preliminary Siting of Future 2A Resources
The Entergy Operating Companies[1] appreciate the opportunity to comment and provide feedback on MISO’s preliminary Future 2A Resource Expansion Plan. This document describes the rationale for the siting recommendations in the associated Excel workbook entitled, ”MISO Preliminary Future 2A Siting – Entergy Response.xlsx” (Siting Spreadsheet) and recommends adjustments to the resource mix in MISO South.
While the Stakeholder Feedback request notes that the resource mix was presented as “final” in the March workshop, Entergy’s comments below also recommend adjustments to the resource mix, given that this is the first time MISO has presented information that is sufficient (and sufficiently detailed) for stakeholders to provide reasonable feedback. Although MISO provided an opportunity for Stakeholders to comment on the resource mix in November 2022, at that time, MISO did not provide the information reasonably needed for stakeholders to comment on the resource mix. For example, it was not until the March workshop that stakeholders were provided with even sub-regional level resource mix information, which was only provided at the MISO footprint level in November, and is not sufficient for providing useful feedback. Foreclosing the opportunity to offer feedback on the resource mix prior to providing information noted above, which is reasonably needed to evaluate and comment on that resource mix, would be unreasonable. For these reasons, Entergy strongly encourages MISO to consider and incorporate the resource mix adjustments recommended here.
Entergy believes that wind will play a role in our future resource fleet, as indicated by the ~11,800 MW of committed wind resources in the preliminary siting, excluding the 5000 MW of “committed” offshore wind sited in Louisiana. Entergy’s comments on future wind installed capacity and siting are based on both the physical potential to produce the forecasted output and the economic potential of developing these resources in the forecasted model years. Regarding considerations of wind energy resource development potential, Entergy stresses the importance of differentiating between onshore wind and offshore wind, which MISO’s current resource selection assumptions do not. As discussed further below, Entergy estimates the approximate Installed Capital Cost of onshore wind at ~$1,500/kW and offshore wind at ~$3,600/kW.
On-shore Wind Capacity Additions
The forecasted addition of ~9,500 MW of on-shore on system RRF wind resources in the Entergy area beyond what is indicated as committed by Entergy is likely impractical and is forecasted earlier than is necessary to meet the relevant Carbon Reduction goals. The F2A resource forecast contains more wind resources than utility scale solar resources in MISO South. This outcome is highly unlikely, and this assumption is thus unreasonable, considering the high cost of wind resources relative to alternatives and the poor quality wind speeds in MISO South. Siting wind in MISO South earlier or in greater magnitude than is realistic would distort the study results relevant to the timeframe of this study and could result in construction of ineffective transmission infrastructure or concealing future system limits.
MISO should share with Stakeholders what has changed to make on system wind resources viable in such high quantity in MISO South, especially by 2032. The RRF wind resources are a significant departure from Future 1, 2 and 3. Future 2 contained only 489 MW of RRF wind resources in MISO South. Future 2A contains ~9.5 GW of RRF wind resources – a nearly 20-fold increase. Adding the RRF wind resources to the Entergy plans (the “committed resources”) creates a massive wind resource fleet build-out. Indeed, with the RRF wind resources, MISO proposes to add more wind in MISO South (26,333 MW[2]) than utility scale solar in the same region (25,584 MW) over the next 20 years. MISO should consider significantly reducing the RRF wind resources in MISO South, especially in PY10, to create a more realistic resource fleet evolution over the next 20 years.
Off-shore Wind Capacity Additions
MISO has sited 5,000 MW of offshore wind as “committed” resources in Louisiana in PY15, presumably representing the Louisiana Governor’s goal to develop 5GW of offshore wind in the Gulf of Mexico by 2035.[3] Entergy notes that the achievability of the Governor’s goal will depend on the economic viability of developing these resources, which MISO's assumptions do not consider. Entergy believes the offshore wind assumption should consider the economics of this resource when comparing the share of the resource mix that is reasonable to assume will be procured to serve load relative to other zero-carbon resource options. To ignore the impact of economics on the attainability of this goal is not a realistic approach to forecasting the future resource mix for the purposes of a large-scale transmission planning study.
As noted by BOEM in its report on Offshore Renewable Energy Technologies in the Gulf of Mexico, there are significant gaps in both cost and technology between offshore wind and other potential energy resources[4] for Current and projected future costs of offshore wind, which are significantly higher than onshore wind and should be differentiated in MISO’s EGEAS inputs. As noted above Entergy estimates the approximate Installed Capital Cost of onshore wind at ~$1,500/kW and offshore wind at ~$3,600/kW; therefore offshore wind at the scale MISO proposes may be ~$10 B more costly than an onshore installation of the same scale , illustrating the importance of both distinguishing the cost of Off-Shore Wind and On-Shore wind when forecasting a resource mix that is intended to represent future resource development. Entergy may support a smaller application of wind offshore (up to 500 MW) in the study models to represent state policy objectives, but it is premature and unsupportable to assume tens of billions in offshore wind investment when substantially less expensive alternatives are available.
Wind & Solar Future Resource Siting
Many of the initially proposed solar and wind resource sites are in densely populated areas of MISO South where adequate land is not available for utility-scale wind development. The Siting Spreadsheet contains many recommendations for moving wind out of sites with inadequate available land and urban areas and into areas more suitable for these types of resources. Generally, if on-system wind does materialize in our region it will likely be in the Mississippi Delta region, central/north Louisiana Delta, or east/north Arkansas.
A significant portion of future Entergy wind resources are likely to come from outside of the MISO region. Entergy recommends modeling 50-67% of wind resources assigned to Entergy in the SPP area. Importing wind from west of our footprint is likely to provide the least cost, highest capacity factor solution in the foreseeable future.
Entergy has provided recommended siting adjustments for solar plants in the Siting Spreadsheet. Generally, sites for solar plants should be selected where land can be reasonably assumed to be available to develop them. A solar plant requires between 5-10 acres per MW. Some sites in the preliminary siting documentation were in densely populated areas, marshland areas or in mountainous areas. The recommended sites avoid these problematic areas that are ill-suited to solar development.
MISO F2A deactivation assumptions generally align with current Entergy assumptions. However, there are two notable units that Entergy requests for the retirement dates to be changed: Ninemile 5 and Sabine 5. Due to the critical nature of both resources (DSG and SETEX resources), Entergy Louisiana and Entergy Texas are preparing these units to remain in-service well into the 2030’s. We recommend replacing the PY5 deactivation assumption with PY15 for both units
Consistent with the MISO siting methodology, brownfield sites should be given priority over greenfield sites for future gas resources. Many of the future gas resources, all of which are “committed” resources, align with deactivations. We provided replacement sites for many greenfield sites that have resources deactivate recently relative to the study year. See Siting Spreadsheet for list of recommended sites for future gas resources.
Demand Response Resource Siting
Entergy has provided recommended siting adjustments for Demand Response in the Siting Spreadsheet. Generally, sites for demand response should be selected where load is available to be reduced. Most sites in the preliminary siting documentation were on substations that do not have load or load that is available to be reduced, such as a power plant auxiliary load. The recommended sites avoid these problematic areas in which assuming substantial Demand Response is unreasonable.
The Siting Spreadsheet seeks to provide the best locations for all the resources in the preliminary siting. However, the recommended off-system wind adjustment may not e represented in the spreadsheet, nor are other resource mix changes. Entergy urges MISO to incorporate the suggested off-system wind and resource mix changes. Correcting the RRF and siting issues is essential to Entergy’s confidence in the business case for, and ability to support, projects resulting from use of the F2A model.
[1] The Entergy Operating Companies are Entergy Arkansas, LLC, Entergy Louisiana, LLC, Entergy Mississippi, LLC, Entergy New Orleans, LLC, and Entergy Texas, Inc.
[2] 5,000 MW of offshore wind is listed as “Committed” in Louisiana and Texas in the MISO siting documentation, both attributed to Entergy Louisiana.
[3] In February, 2022, Louisiana Governor John Bel Edwards’ Climate Initiatives Task Force set a target of 5 GW of installed offshore wind capacity by 2035 in its first-ever Climate Action Plan (https://gov.louisiana.gov/assets/docs/CCI-Task-force/CAP/Climate_Action_Plan_FINAL_3.pdf)
[4] Offshore Renewable Energy Technologies in the Gulf of Mexico (boem.gov) (https://www.boem.gov/sites/default/files/documents/regions/gulf-mexico-ocs-region/Offshore-Renewable-Energy-Technologies-Gulf-Mexico-Fact-Sheet.pdf). The projections produced for BOEM by National Renewable Energy Lab (“NREL”) reflect a rate/cost that is not competitive with other renewable resources available in the Gulf South region, even as far out as 2030 when BOEM notes that the rapid improvement in the economics for offshore wind “make economic deployment of offshore wind turbines in the Gulf of Mexico likely by 2030, when costs may be approaching acceptable market levels.” NREL has also completed a more recent studyfunded by BOEM (Offshore Wind in the U.S. Gulf of Mexico: Regional Economic (boem.gov)),
Feedback from the Mississippi Public Service Commission was submitted via email to Stakeholder Relations.
ATC appreciates MISO's work on the LRTP Futures Update and generation expansion siting process. After reviewing the proposed expansion siting, ATC has the following observations and comments.
ITC appreciates the opportunity to provide feedback on the F2A siting process. The updated renewable energy additions are a welcome sight as the clean energy aspirations across this industry continue to grow. We look forward to working together throughout the LRTP process.
As we reviewed the bus level siting in Michigan, we have concerns with the utility scale wind, solar, and storage siting in Southeast Michigan, specifically Oakland, Wayne, and Macomb counties. These areas are highly developed and scattered with prized state & recreational parks. We do not specify bus alternatives, but good candidates could be found in te Michigan Thumb Region and along the Southern parts of Michigan between Palisades and Monroe substations. We also identified a handful of committed units with bus siting that needs to be corrected. Additional detail will be submitted via the siting workbook.
For Iowa, MISO should also use the current active queued generation as the guiding basis for siting some RRF generation. The queue is a strong indicator of where each type of resource is likely to be viable for siting and construction. With a form of site control being required to enter the queue, it helps demonstrate that there is some amount of local landowner support for projects to be constructed in an area.
For example, there is a large amount of RRF resources in the area southwest of the Des Moines Metro (Madison, Dallas, Polk, and Warren counties) but there are not many requests here in the current MISO queue, likely due to local opposition to such projects. Conversely, there is not much RRF generation in the area between Marshalltown and Cedar Rapids areas (Marshall, Tama, and Benton counties) but there are current queue requests in this area which will be supported the approved Tranche 1 projects that will be built through this area of the state. In addition, the northeast Iowa area has several requests currently in the queue, yet MISO has no proposed RRF generation in that portion of the state.
Thanks,
ITC Planning
GRE supports the MISO LRTP effort to address the rapid and ongoing generation portfolio transition reliably and efficiently. The LRTP along with the wider Reliability Imperative help meet the Minnesota clean energy standards and GRE policy goals.
Thank you for providing initial resource expansion and siting details as this helps foster stakeholder review and feedback early in the futures and model development process.
• GRE supports the added scope to validate energy adequacy in the MISO footprint of the non-chronological EGEAS expansion results with a chronological tool (PROMOD).
• From the F2A retirements spreadsheet provided with the March 8th PAC meeting materials and the LRTP T2 Workshop #2 preliminary Future 2A siting spreadsheet of resource additions, there are some inconsistent generator names and siting information and GRE has some general comments on RRF generator siting.
• GRE urges MISO to consider including LRTP T2 transmission in North Dakota to connect the present MISO islands in ND. By providing contract path to these islands and connecting them with greater MISO transmission system, MISO generation interconnections could occur there without being subject to transmission rate pancaking
• Currently RRF generation siting in southeastern MN is highly concentrated to a few buses on the Minnesota / Iowa border. GRE would suggest MISO provide greater reliance on the Generator Interconnection Queue for guidance on RRF generation siting.
• Include more variations of storage battery types other than just 4-hour duration. Storage technology will improve to include various duration capabilities to address different market services. For dispatchability benefits, a pumped hydro project on the Iron Range could be included in the resource expansion.
The Environmental Sector appreciates the opportunity to submit this set of feedback regarding the preliminary Future 2A siting results. Updating the MISO Futures is a vitally important practice to ensure that transmission planning occurs in a timely fashion with the most up-to-date information available. We applaud MISO’s efforts to keep the Futures updated, and it appears the Environmental Sector’s December 2022 comments were widely accepted.
A new analysis from the National Renewable Energy Lab evaluated the impacts of the federal Inflation Reduction Act (IRA) and the Bipartisan Infrastructure Law (BIL). The analysis found that, “Clean electricity shares could increase substantially with IRA and BIL, rising from 41% in 2022 to a range of 71%–90% of total generation by 2030, across the range of scenarios considering uncertainties in future technology costs, fuel prices, policy impacts, and deployment constraints.” NREL’s study provides an independent analysis that underscores and supports MISO’s revision of the Futures and the anticipated high levels of clean energy additions over the next 20 years.
Future 2A Retirements Data
MISO provided stakeholders with the modeled retirement dates associated with existing generation facilities in the footprint (“MISO F2A Installed Capacity Additions and Retirements (GW)*”). Specific data regarding individual unit retirements are also available (“20230308 PAC Item 08a MISO F2A Retirements.xlsx”) at the PAC on March 8, 2023. While we understand that this specific feedback request did not include all of those data, we feel it is important to include a discussion regarding the retirement assumptions.The Environmental Sector requests that MISO continue to use the most up-to-date information regarding retirement assumptions and provide a comparison of Future 2A proposed retirement analysis dates with the previous Future 1, 2, and 3 assumptions (“Series 1”) and denote any changes between the two data sets (Series 1 versus Series 2).
For example, in the Future 2A retirement data, some portions of the Independence 1 and 2 coal-fired power plants located in Arkansas are listed as retired within the 5 year time horizon, but listed as an “Unknown LRZ 08” resource. Independence 1 and 2 are jointly owned by Arkansas Electric Cooperative Corp. Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, and Entergy New Orleans. The portions selected to retire within the 5 year window add up to 1,009 MW of the 1,663 MW listed in the MISO retirement worksheets, with the remaining 654 MW retiring within the 10 year window. By court order, Independence 1 and 2 are required to close by December 31, 2030. In the Series 1 Futures (Future 1, 2, 3), Independence 1 and 2 were all assumed retired by the Year 10 window. However, in this Series of Futures, we recommend that all of Independence 1 and 2 should be included in the 5 year window for retirement.
The White Bluff units 1 and 2 coal-fired power plants located in Arkansas are slated for retirement by December 31, 2028 by the same court order; however, in the current retirement model for Future 2A, those units are not slated for retirement until the Year 10 study window. Those two units account for 1,647 MW of nameplate capacity. The Series 1 Futures had White Bluff 1 and 2 retiring in the 5 year window for Future 2 and Future 3, and only in Future 1 was White Bluff considered in the Year 10 retirement window. All of White Bluff 1 and 2 should be included in the 5 year window for retirement, given its earlier retirement timeline compared to Independence 1 and 2.
As a part of scenario-based planning, Entergy’s various IRPs (in Arkansas and Mississippi, for example) include scenarios for earlier retirement for both White Bluff and Independence coal-fired generation, within the 5 year window. Entergy Arkansas noted, “The primary driver for the next significant capacity deficit after 2025 will coincide with the timing of the cease-to-use coal (“CTUC”) efforts at White Bluff and Independence. That timing will be no later than 2028 for White Bluff and 2030 for Independence but could be sooner.” In keeping with scenario based planning practices, it would make sense to include the “could be sooner” provision regarding both Independence and White Bluff in Future 2A and eventually Future 3A.
The retirement assumptions may also need to be revisited for Indiana. For example, F B Culley:3 is shown as "out of study period" for all futures. CenterPoint's latest IRP slides (slide 46) shows under every "Draft Optimized Portfolio" that CenterPoint would retire the unit in 2029 - well before the end of the Futures study period. AES Indiana (or, Indianapolis Power and Light) is converting its coal-fired Petersburg units 3-4 (1,052 MW) to natural gas steam (not a CC, not a CT) in 2025, and should be reflected as such in the data.
Additionally, the retirement data for Future 2A also includes a number of generic units by generation technology types including CC (combined cycle natural gas), CT (combustion turbines), DGPV (distributed generation photovoltaics), Hybrid, IC Gas (internal combustion), LIBAT (presumably lithium-ion batteries), PV, and Wind. The generic units appear to be new units that are added at some point over the 20 year horizon that would then be retired at a later date beyond the study horizon. In effect, the generic units appear to be some level of generator additions included in the retirements data set. Slide 5 of the March 10 presentation regarding this topic shows additions to add up to 333 GW; however, the retirement data set for the new generic units additions (provided to the PAC on March 8, 2023) for all technology types adds up to only approximately 100 GW, and the total data set amounts to 246.6 GW of capacity that exists “Out of Study Period”. Perhaps the difference between the two data summaries is what is manually provided to the model (the 100 GW in the retirement model for new units, and 146 GW of existing units) versus what is model selected (the remainder, or 233 GW). If so, the Environmental Sector would appreciate some clarification.
It appears that DGPV unit additions are severely underrepresented in the “retirements” data set (provided to the PAC on March 8), accounting for only 24.7 MW in the entire “retirements” dataset, and all located within Southern Indiana Gas & Electric’s territory. DR also appears to be underrepresented, accounting for approximately 4.6 GW worth of resources.
Additionally, the retirement spreadsheet provided to the PAC on March 8, 2023 does not include the technology type of the existing (named) generation units assumed to be retired over the next 20 years. It would be difficult to match existing retirement assumptions with fuel type without manually designating each generator type. The Environmental Sector requests that the retirement data be provided in a fashion so that stakeholders can re-create Slide 5 of the Future 2A Expansion & Preliminary Siting presentation.
Future 2A Additions Data
The Environmental Sector evaluated the Future 2A capacity additions based on the quantities of additions, the timing of such additions, and finally, location. The data were provided at the LRTP Workshop on March 10, 2023 (“20230310 LRTP Workshop Item 02 MISO Preliminary Future 2A Siting.xlsx”). At a high level, the resource additions appear to be fairly reasonable; however, upon closer inspection, there appear to be a number of disjointed components of the Future 2A additions that need to be remedied.
Wind Resources
For wind, Future 2A adds 18 GW in Y5, 58 GW in Y10, 43.5 GW in Y15, and 26 GW in Y20 for a total addition of roughly 146 GW by 2042. There are currently 24,750 MW of wind generation resources in the MISO queue. Broadly, the ramp-up of wind additions tracks well with the implementation of the Inflation Reduction Act, given that federal tax credits have been extended through the end of the 2020s.
The state-by-state breakdown of wind resources appears to be fairly reasonable; except for Louisiana, Louisiana adds over 15 GW of new wind resources, while solar resources reach just 10 GW. Of the wind from Future 2A, 9.6 GW are “committed” in Louisiana, mostly in Y20, and 5.9 GW are RRF model-built resources, almost entirely in Y10. While the offshore wind opportunities for Louisiana are quite high, offshore wind appears to be just 2.5 GW worth of Louisiana’s total wind capacity within the modeled 15 GW; thus, the remainder of the wind resources in Louisiana are assumed to be in-state land-based wind, a high amount given the amount of wind in the Louisiana queue currently.
Some wind additions provided in the model data seem highly unlikely to come to fruition. For example, some 3.5 GW of wind resources are added to St. Charles Parish, Louisiana in the dataset. St. Charles Parish is located just to the west of New Orleans, and is heavily defined by local swampland with few opportunities for development. Several other Parishes contain similar land use constraints, but contain high quantities of wind development per the Future 2A dataset. Of the 34 GW of resources currently in the queue for Louisiana, only 230 MW are wind, and zero megawatts of any resource are being evaluated for St. Charles Parish, likely due to the land use constraints. It appears that MISO may be relying on Entergy Louisiana’s draft IRP Portfolio 2 for the quantity of wind added; however, that Portfolio has been recognized as unlikely in the stakeholder process and, regrettably, that portfolio does not include any offshore wind. Regarding onshore wind in Louisiana, the Environmental Sector recommends MISO 1) maintain the offshore wind component and/or increase the amount, 2) allow wind imports from out-of-region (like SPP), and/or 3) reduce the amount of wind assumed in the model due to land use constraints and replace those resources with hybrid resources. Finally, we encourage MISO to provide clear explanations for the methodologies and source documentation regarding quantities of all resources across the footprint.
Regarding offshore wind specifically, the Environmental Sector requested offshore wind be included in Future 2A in our December 2022 comments and we are pleased MISO is including offshore wind, particularly for the Gulf of Mexico. A National Renewable Energy Lab report highlights the potential for offshore wind in the Gulf of Mexico and supports its inclusion in the Series 2 Futures updates. However, we object to MISO’s stated plan to use onshore wind generation profile data to model the proposed offshore wind generation near Texas and Louisiana. Offshore wind’s generation profile is unique and distinct from onshore wind resources. Offshore wind resources typically provide significantly higher capacity values compared to onshore wind due to the diurnal sea breeze effect. This bears out in ERCOT’s higher capacity evaluation for coastal onshore wind projects that share similar characteristics to offshore wind projects. The National Renewable Energy Lab’s Wind Prospector toolkit provides sub-hourly generation models for offshore wind near Southwest Louisiana and Southeast Texas for multiple years (1.3 gigabyte download available). The Bureau of Ocean Energy Management (BOEM, the federal agency in charge of offshore wind lease sales) includes NREL data for hourly wind speed values in the Gulf of Mexico, as well as other regions. The data are available for download. We recommend MISO use an offshore wind profile for offshore wind projects.
Further on offshore wind, the two points of interconnection might be reasonable; however, both are listed as 230kV connections. We recommend MISO evaluate whether the interconnections should be relocated to the nearby 500kV system.
Solar Resources
For solar, Future 2A adds 37.5 GW in Y5, 28 GW in Y10, 20 GW in Y15, and 21 GW in Y20 for a total addition of roughly 107 GW by 2042. There are currently 141,814 MW of solar generation resources in the MISO queue. Broadly, the ramp-up of solar additions tracks well with the implementation of the Inflation Reduction Act, given that federal tax credits have been extended through the end of the 2020s.
DGPV
While the data provided are not clear, it appears that roughly 17 GW of solar is designated as distributed generation (DGPV) while nearly 90 GW are designated for utility-scale. Most of Indiana’s DGPV (1.3 GW of 2.1 GW) is added in Y5, while most of Louisiana’s DGPV (1.8 GW of 2.1 GW) is added after Y15. Most states add zero MW of DGPV in Y5, including Arkansas, Illinois, Iowa, Louisiana, Michigan, Mississippi, Montana, North Dakota, Texas and Wisconsin. In fact, Y15 has the highest level of DPGV additions compared to any of the other years, beyond the time horizon for the Inflation Reduction Act tax credits. This is an unrealistic set of assumptions that no DGPV would be added for most of MISO’s states over the next five years.
Specifically regarding individual county levels of DGPV, the Environmental Sector recommends MISO conduct a “gut check” with regards to the proposed quantities deployed. For instance, in Indiana the highest level of DGPV deployment is slated for Lake County (550 MW) while Marion County, the state’s most populous county, is slated for just 200 MW of DGPV deployment. Indiana currently has a total of 192 MW of net metering solar capacity currently installed, which would likely be designated as DGPV. However, net metering ended effective July 1, 2022. Based on the policy change, the 1.2 GW of DGPV in Indiana seems overly ambitious, especially within the next 5 years (Y5). In Missouri, Boone County has the highest level of DGPV (500 MW) while being the state’s 8th most populous county, while St. Louis County has less DGPV (350 MW), but nearly six times more people. MISO should provide narrative explanations for the DGPV build out assumptions and/or update DGPV siting and build out assumptions.
Broadly, it appears that DGPV are provided to the model in 50 MW increments. We recommend that MISO consider adding smaller amounts of DGPV in a more evenly distributed fashion.
Utility-Scale PV
The highest levels of utility-scale solar additions include Michigan (17 GW), Indiana (12 GW), and Minnesota (11 GW). Louisiana’s utility-scale solar additions amount to nearly 8 GW. All other states have less than 6.2 GW of solar additions over 20 years. Kentucky (1.1 GW) and South Dakota (0.8 GW) are the states with the least solar additions over the Future 2A time horizon. North Dakota adds nearly 2.5 GW, or three times as much solar as South Dakota, which seems like an unusual distribution. Comparably, Louisiana’s 8 GW seems low given that state’s high level of solar irradiance and southerly location. The Environmental Sector recommends that MISO cross-compare the proposed solar build-out with the current generation interconnection queue locations, and ensure that land use considerations are reasonably incorporated (e.g. sensitive areas and areas with little land availability should be de-prioritized).
Hybrid Resources
For solar hybrid resources, Future 2A adds 1.2 GW in Y5, 3.3 GW in Y10, 3.5 GW in Y15, and 2 GW in Y20 for a total addition of roughly 9.8 GW by 2042. There are currently 47,053 MW of hybrid generation resources in the MISO queue. In Future 2A, no new hybrid resources are added in Y5, with the exception of Wisconsin (1.1 GW) and Indiana (75 MW). No hybrid resources are added in Iowa, Kentucky, Missouri, Montana, nor North Dakota until Y15, and even then, all those states add less than 215 MW over the next fifteen years. Louisiana only adds 50 MW of hybrid resources in Y10, and then none at any other time. Mississippi and Montana add no hybrid resources over the next 20 years, which seems like a highly unlikely situation. The Environmental Sector recommends that MISO cross-compare the proposed hybrid build-out with the current generation interconnection queue locations, and significantly increase the amount of hybrid additions over the next 20 years, especially in Y5.
Battery Storage Resources
For battery storage resources, Future 2A adds 0.5 GW in Y5, 3.5 GW in Y10, 13 GW in Y15, and 10.5 GW in Y20 for a total addition of roughly 27.9 GW by 2042. Nearly 20 GW of those resources were identified as RRF resources. There are currently 46,021 MW of battery storage generation resources in the MISO queue. For Y5, only 552 MW of battery resource additions are added, mostly in Michigan (182 MW) and Wisconsin (175 MW). Overall, MISO’s expansion of battery storage seems to fall short of expectations and we encourage MISO to revisit the storage deployment assessment, just as we recommended in our December 2022 comments.
Michigan has the highest amount of battery storage additions over the next 20 years, with just over 5 GW added, or almost 20% of all batteries deployed. Indiana has nearly 4 GW deployed, and Wisconsin and Minnesota each having 2.5 GW and 2.2 GW of batteries deployed, respectively.
In the data, some LBA/Areas seem disjointed from where proposed battery deployments exist. For example, several LBA Entergy New Orleans battery resources are deployed in Mississippi. For Entergy Mississippi, some of the battery resources are deployed in Louisiana, and in areas not close to the Mississippi border (like Calcasieu Parish). While we generally support optimizing generation, regardless of geographic location, it seems unusual that batteries for an LBA would be sited far away from its natural footprint. We request some insight into why batteries may be sited far away from their intended customers.
The Environmental Sector recommends that MISO develop a portfolio of distributed battery resources, similar to the DGPV resources. Given the likelihood that Order 2222 will expand distributed battery deployment, alongside the Inflation Reduction Act benefits, now is the time to incorporate these resources for planning purposes. We suggest these resources be designated as LITDG (for distributed generation lithium batteries) and be deployed in similar fashion to the DGPV resources.
Electric Vehicles
Currently, the MISO data does not clarify assumptions regarding electric vehicle (EV) adoption rates and dispatchability. Like these comments, EV’s may fit somewhere between a DGLIT resource capable of being dispatched in a vehicle-to-grid fashion in some states, or as a demand response resource where EV charging is directly controlled down as an aggregated resource. With the implementation of Order 2222, EV’s will become a growing source of controllable, dispatchable load and/or generation. The Environmental Sector recommends MISO include EV growth as distributed energy resources after Order 2222 implementation, as in, by Y5.
Demand Response
For demand response resources, Future 2A adds 9.8 GW in Y5, 183 MW in Y10, 315 MW in Y15, and 181 MW in Y20 for a total addition of roughly 10.5 GW by 2042. The largest states with DR resources include Minnesota (2.7 GW), Michigan (2 GW), Indiana (1.1 GW) and Wisconsin (0.8 GW). All other states have somewhere between 293 MW - 648 MW worth of DR resources. The anemic additions of new DR over planning years Y10, Y15, and Y20 is puzzling, given the likelihood that Order 2222 will enable greater demand response programs and that demand response resources will become increasingly valuable as renewable energy penetration levels increase. MISO’s proposed implementation date of Order 2222 is 2029 and so one would expect the DR Resources to increase more dramatically after Y5. It is exceptionally bizarre that a state like Louisiana, which has significant industrial load, would have zero new DR capacity past Y5, and only accounts for 340 MW of DR in Future 2A. As green hydrogen production increases across MISO, new large loads may be added that are capable of providing demand response. Demand response is an important tool for ensuring system reliability and may be more highly valued for its effective capacity contributions over the next 20 years. We recommend MISO evaluate DR potential and include higher levels of DR appropriately across the footprint.
Natural Gas Resources
There are currently 6,955 MW of natural gas generation resources in the MISO queue. Future 2A adds 20.5 GW of new gas resources over the next 20 years including a mix of both CT and CC units. Few natural gas RRF CT and CC units are added. An additional 542 MW of “other” gas resources are added that are made up mostly of reciprocating engine (RICE) facilities. RICE units are only added in Entergy, Consumers, Iowa and Wisconsin territories and none are RRF units, highlighting the limited deployment of those facilities. It appears that potentially all states add some level of new gas units over the next 20 years, with Minnesota (3.7 GW), Michigan (2.9 GW), Indiana (2.6 GW), Illinois (2.5 GW), and Louisiana (2.4 GW) adding the most. The Environmental Sector requests clarity whether these resources are anticipated to include any level of carbon capture sequestration (CCS) or hydrogen burning capability.
We encourage MISO to evaluate if these new facilities have gas pipeline capacity available and/or to locate these new facilities at retiring facility locations to re-use the existing points of interconnection.
Hydrogen Resources
Notably absent from the Future 2A discussion is the treatment of new hydrogen-fueled generation resources, such as thermal combustion, as well as new hydrogen load created from a growing electrolysis industry. It may also be worth looking at how siting may differ depending on whether hydrogen electrolyzers are co-located with load or near generating resources. Considering the difficulty in transforming existing gas infrastructure into hydrogen infrastructure, it is perhaps likely that the former is the most likely scenario. The Environmental Sector would invite a discussion about including hydrogen generation resources, as well as new hydrogen electrolyzers as load growth.
HVDC
Several proposed HVDC resources should also be included in Future 2A. For example, there is currently a 1,500 MW interconnection request for an HVDC resource in Mississippi. Also, the Grain Belt Express project would interconnect with MISO to provide 2,500 MW of power and capacity. Both projects would import significant amounts of non-MISO resources into the MISO system. Excluding these resources in an “advanced” portfolio like Future 2A would have a similar system impact to excluding a new nuclear reactor’s worth of energy and capacity - the impact would be huge. We request that these resources, and any other HVDC resources that may be added, be included in Future 2A.
Carbon Capture Sequestration/Small Modular Reactor Resources
Notably absent from the Future 2A discussion is information regarding CCS and SMR’s. Coal Creek CCS 1 and 2, for a total of approximately 160 MW, are included for Great River Energy in North Dakota in the Y5 planning year and are listed as an “Other” generator type, as opposed to coal. The Environmental Sector would like clear information regarding CCS and SMR units as potential resources. Potentially in Future 3A, MISO can include its “unicorn” generation technology, the "Low emissions, high capacity factor, dispatchable" facilities discussed at the November 10, 2022 Regional Resource Assessment Workshop.
Montana
While there are currently no resources in the Montana portion of MISO’s generation interconnection queue, it is highly unusual that Montana only adds 88 MW of gas in Y5 and 49.5 MW of wind in Y15 in Future 2A. We recommend a deeper dive into Montana’s generation mix over the next 20 years.
Futures 1A, 3A
When MISO first began the “Futures Evolution” discussion, Futures 1, 2, and 3 were discussed simultaneously; where Future 1 was meant to represent a conservative or business-as-usual case and Future 3 was meant to represent the most advanced case. As history has shown, even with the Series 1 of Futures 1, 2, and 3, our forecasts in the future have rapidly changed - Future 2 now resembles Future 1A, and Future 3 now resembles Future 2A. In our December 2022 comments, the Environmental Sector made several recommendations regarding Future 3A. We request that MISO include an update regarding Future 3A development and engage stakeholders in discussing the scoping of that future sooner rather than later.
The purpose of scenario-based planning is to provide “bookends” of potential futures where transmission proposals are tested across multiple futures. Unfortunately, MISO seems to be stepping away from using the full breadth of the bookends and is instead relying on individual futures for each new “tranche” of the Long Range Transmission Planning process. Not only does this provide a much less robust set of analysis for each transmission line, it also potentially causes a lag in transmission planning that we do not have the luxury in entertaining anymore. As envisioned, using all three Futures has been the hallmark of smart planning practices, as recognized by the Federal Energy Regulatory Commission’s Notice of Proposed Rulemaking regarding regional (and soon, interregional) transmission planning. We are concerned that MISO and the stakeholders at large are stepping away from scenario based planning practices and we encourage the use of all Futures simultaneously, as originally envisioned five years ago.
The Environmental Sector appreciates MISO’s willingness to share data from Future 2A on both the retirement and additions side of the generation equations in the newly developed "Future Planning Scenarios" webpage. Stakeholders are able to provide much more robust commentary when data are easily shared and available. We request that MISO also provide the retirement and additions data of Future 1A in similar fashion to the data provided regarding Future 2A to create continuity of information sharing on the "Future Planning Scenarios" webpage, and prepare to do the same for Future 3A.