West Technical Study Task Force (WTSTF) - October 2, 2023

Meeting Information

Details

Webex Information:

Event Number: 2493 515 7485

Event Password: AM1002

Please log into Webex to access the dial in information.

MISO received an Expedited Project Review (EPR) request from Montana Dakota Utilities on August 22nd for a new customer addition with a 50 MW facility.  The new customer load will be served from MDU’s 41.6kV system at the Leola Substation. Additionally, Expedited Project Review from ITC Midwest to build a new interconnection load at the Winnebago, MN.

Meeting Materials