MISO received an Expedited Project Review (EPR) request from BREC on September 13, 2024, proposing BREC Bon Harbor to OMU Sub ‘M’ 69 kV Interconnection. The project is needed to connect the existing OMU Substation “M” to BREC’s existing 69 kV Bon Harbor Line. The required in-service date of the project (ISD) is December 2026