MISO Dashboard

Last Modified - 10/18/2023

MTEP Selection of Non-Transmission Alternatives (fka IR092) PAC-2020-2

2021 2022 2023
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
E
FERC
D
D
D
D
D
B
B
I

Overview

As submitted: The MTEP process as currently structured does not truly consider non-transmission alternatives on a level playing field to transmission solutions. Although MISO developed Business Practices with the PSC/PAC during calendar years 2015-2016 to address the tariff requirements for comparable treatment of non-transmission alternatives, the process has limitations. These limitations result in Transmission solutions almost always being developed as the default option to system issues with limited opportunity for non-transmission alternatives. For example, new generation or energy storage is required to have a signed interconnection agreement to be evaluated in the MTEP process as an alternative to a transmission solution. With the current interconnection process regularly taking over 1000 days, it is effectively impossible for MISO to evaluate or select a new generation alternative to address a system issue identified in MTEP. Moreover, MISO’s requirements for evaluating and selecting other non-transmission alternatives are not clearly specified. For example, there is no policy for evaluating the use of a retired generator converted to a synchronous condenser as a non-transmission alternative.  An approach that seeks to balance both cost and reliability must be found.

This issue was submitted by DTE Energy in January 2020.

(formerly IR092)

Updates

Sorry, no results were found that match your query.